Foundation Cost Calculator & Thickened-Slab Takeoff
Use the dimensions of a documented rectangular slab foundation to compare two written concrete bids. Separate the full slab, thickened perimeter and two centered interior strips. See the exact cubic-yard impact of their crossing, how much each bid includes, and its total on the entered scope.
Compare foundation concrete and written bids
See how the slab, perimeter and intersecting strips contribute to the quantity each quote must cover.
Inspect the takeoff and bid quantities
Strip crossing · 2.25 ft² · 10 in extra depth · 0.06944444 yd³
Review the takeoff and exact CSV
| Layer | Area (ft²) | Depth (in) | Volume (yd³) |
|---|---|---|---|
| Full slab | 432 | 4 | 5.33333333 |
| Perimeter band | 117 | 8 | 2.88888889 |
| Lengthwise strip outside crossing | 29.25 | 6 | 0.54166667 |
| Crosswise strip outside crossing | 20.25 | 10 | 0.625 |
| Strip crossing | 2.25 | 10 | 0.06944444 |
| Charge | Quote A | Quote B |
|---|---|---|
| Included concrete | $1,634.40 | $1,732.50 |
| Outer forms | $840.00 | $756.00 |
| Other written scope | $4,900.00 | $5,000.00 |
| Entered total | $7,374.40 | $7,488.50 |
How to use this calculator
- Enter the footprint and continuous slab thickness shown on your written plan.
- Enter the perimeter band and both centered strips using their extra depths below the slab. Use zero width and depth for an absent layer.
- Enter the chosen allowance. Inspect the plan drawing and how much concrete each layer contributes.
- For each written quote enter included quantity, concrete unit rate, outer form rate and all other included work. Compare quantity coverage first and export the exact ledger.
The Formula
The mathematical logic powering this calculation is:
Use a single rectangular footprint from an existing documented plan. The full slab covers length × width at base thickness. The perimeter band has area L × W − (L − 2e)(W − 2e), where e is the band width in feet. The two centered interior strips stop at the inner edge of the perimeter band. With inner lengths IL and IW, and strip widths s along the length and t across it, their exclusive areas are s × (IL − t) and t × (IW − s). The crossing s × t is a single region at the deeper of the two entered extra depths. Extra depths start below the base slab. A projected shape with additive depths at the intersection needs a different takeoff.
Each zone volume in cubic yards is square feet × thickness in inches ÷ 324. Add the zone volumes exactly, then multiply by 1 + allowance percentage ÷ 100. Compare the resulting quantity with each written included amount. An exact match covers the modeled quantity. Only quotes that include at least that amount qualify for cost ranking. The worksheet keeps the price of any short quote visible.
Each entered total adds quoted concrete yards times its unit rate, the outer perimeter 2(L + W) times the entered form rate, and other written charges. Material and forms each round half up to cents. Enter equivalent documented scope for both quotes. Use a zero rate for charges already included elsewhere. The outer form rate applies only to the outer boundary. Separately requested items must be included in the written fixed line once.
Outside sides accept 1–1,500 ft, base thickness 0.1–48 in, extra depths 0–96 in and allowance 0–50%, each with up to three decimals. An inactive thickening has zero width and zero extra depth. Quote amounts accept 0.001–2,000,000 yd³ with three decimals and USD charges with two. The example amounts are illustrative. This takeoff assumes squared corners and rectangular prisms at the entered depths. It does not evaluate reinforcement, bearing capacity, installation, code, pump access or the suitability of any foundation dimensions.Worked Example
If you input:
- Footprint: 24 × 18 ft
- Slab: 4 in thick
- Perimeter band: 1.5 ft wide × 8 in extra depth
- Centered strips: 1.5 ft wide each, 6 in and 10 in extra depth
- Allowance: 8%
- Included concrete: Quote A 10.215 yd³, Quote B 10.5 yd³
Result:
The net foundation is 227/24 yd³. With the 8% allowance, exactly 10.215 yd³ is required. Both quotes cover that quantity, and Quote A’s $7,374.40 total is lower. At 8.001% allowance, A is short by 227/2,400,000 yd³.
Frequently Asked Questions
Why is the strip crossing counted once?
The two strips describe intersecting solid regions. The deeper extra depth determines the concrete under their shared footprint. Adding both would count the shared material twice.
What if my foundation is a plain slab?
Enter zero width and zero extra depth for all three thickened areas. The full slab retains its entered thickness and volume.
Can I enter basement walls, isolated pads or a strip that leaves the rectangle?
This worksheet supports a rectangular slab with the displayed perimeter band and centered internal strips. Those other geometries need their own measured takeoff.
Why is a cheaper bid sometimes excluded from the comparison?
A bid may quote a smaller concrete volume. Compare complete documented scopes at the modeled required quantity before choosing between totals.
Does the tool tell me what slab thickness to use?
Enter dimensions from the documented plan. The worksheet measures the modeled concrete and costs; design and local approval depend on the actual site and project.
Do the quoted yards change when I edit the allowance?
The required quantity changes. Each bid retains the written included amount until you edit it, so a coverage gap remains visible.
Similar Calculators
Foundation Squaring Calculator & Rectangle Layout Planner
Find the diagonal of a planned rectangle or audit four measured corners. Compare both tape diagonals and see estimated corner moves against your target.
Concrete Slab Calculator
Estimate concrete slab volume, cubic yards, bag count, waste allowance, and material cost.
Concrete Slab Pour Schedule & Delivery Quote Planner
Compare ready-mix concrete delivery quotes for a slab pour. Schedule individual loads, check the site cutoff and calculate short-load and overtime charges.
Foundation Repair Quote & Depth Planner
Compare foundation repair quotes across supplied pier depths. Audit included-depth allowances, per-pier billing increments, fixed scope and missing prices.