Concrete Slab Pour Schedule & Delivery Quote Planner

Start with your already measured order requirement and compare two written ready-mix delivery quotes. Allocate loads, model a single unloading position and inspect each truck’s timeline. Compare billed amounts only after checking whether both plans clear the site cutoff you entered.

Ready-mix delivery

Compare concrete truck schedules and charges

See how truck spacing and closeout affect the quote total and your site cutoff.

Both schedules fit. Quote B is $74.25 lower.

Quote A
$3,008.75
16.25 yd³ on 3 trucksFinal release at minute 68 · 17 min headroom33 min truck queue · 0 min crew idle
Quote B
$2,934.50
16.5 yd³ on 3 trucksFinal release at minute 84 · 1 min headroom0 min truck queue · 15 min crew idle

Truck timing and access cutoff

Compare arrival, waiting, placement and release on the same minute scale.
Minute 0Access cutoff at minute 85Minute 85
  • Dashed brown · queue
  • Solid teal · placement
  • Dotted violet · closeout
Arrival
0 min
Placement starts
0 min
Placement ends
24 min
Released
28 min
Edit site clock and delivery quotes
Shared site scenario

Use whole minutes from the same clock origin for the crew, truck arrivals and cutoff.

Quote A delivery terms
Quote B delivery terms
Open truck and charge ledgers

Quote A itemized costs

Material
$2,518.75
Delivery
$210.00
Short loads
$140.00
Overtime
$140.00
Fixed quote
$0.00
TruckLoadArrivalStartReleaseQueueOvertimeTruck cost
17 yd³0 min0 min28 min0 min1 blocks$1,190.00
27 yd³17 min28 min56 min11 min2 blocks$1,225.00
32.25 yd³34 min56 min68 min22 min1 blocks$593.75

Quote B itemized costs

Material
$2,623.50
Delivery
$246.00
Short loads
$0.00
Overtime
$0.00
Fixed quote
$65.00
TruckLoadArrivalStartReleaseQueueOvertimeTruck cost
15.5 yd³5 min5 min28 min0 min0 blocks$956.50
25.5 yd³33 min33 min56 min0 min0 blocks$956.50
35.5 yd³61 min61 min84 min0 min0 blocks$956.50
Open selectable CSV

How to use this calculator

  1. Enter the required concrete volume from measured slab quantities, your crew’s estimated placement rate and the common site clock.
  2. Copy the capacity, increment, arrival schedule and loading arrangement from each quote.
  3. Enter all comparable prices and choose whether the short-load fee applies at exactly the stated threshold.
  4. Compare final truck releases with the cutoff. Inspect the truck timing chart and export the detailed charge ledger.

The Formula

The mathematical logic powering this calculation is:

Use one positive required volume V in cubic yards, including any allowance already chosen with your supplier. Each quote delivers the smallest whole multiple of its order increment u that meets V. The entered usable truck capacity must be a whole multiple of u. Divide the ordered increment count by the truck’s capacity in increments and round upward for the truck count. Fill trucks in order to capacity, or distribute the ordered increments as evenly as possible, assigning one extra increment to the earliest trucks when needed. A quote never changes the required volume.

Use a common clock in whole minutes from your chosen start of day. Arrival = first arrival + zero-based truck number × spacing. There is one unloading position. Start = the later of arrival and the previous release, using crew-ready time for the first truck. Placement duration is the whole-minute ceiling of 60 × delivered yd³ ÷ crew rate in yd³/hour. Release adds the entered full closeout minutes after placement. The next truck cannot start before that release. Queue = start − arrival. Crew idle = start − previous release. The first idle uses crew-ready time. On-site time = release − arrival and includes waiting, placement and closeout. Compare final release to the entered access cutoff; equality fits that planning window.

Material is delivered volume × written rate, rounded half up to a cent on each truck. Add a per-truck delivery charge. A truck below the entered short-load threshold incurs the flat short-load fee. The inclusive rule also charges at exact equality. Charge overtime blocks = ceiling[max(0, on-site minutes − included minutes) ÷ written block minutes]. Multiply by the entered charge per block, then sum all truck charges and add the fixed quote charge once. Include applicable taxes or omitted items in your own comparison before using it as a full project cost.

Supports 0.01–200 yd³ target volume, 1–120 yd³/hour placement rate and up to 12 loads per quote. Volume and money accept up to two decimals; clock inputs are whole minutes. Release and cost are modeled using one fixed rate and even dispatch spacing. Access cutoff is an entered logistics constraint, independent of concrete quality or a job specification. Verify actual dispatch, placement, access and discharge requirements with the producer. No travel delay, batching time, mix behavior, placement practice, legal load capacity, crew productivity or structural requirements are supplied by the planner.

Worked Example

If you input:

  • Required concrete (yd³): 16.20
  • Placement rate (yd³/hour): 18
  • Closeout per truck (min): 4
  • Access cutoff at minute: 85
  • Quote A: 7 yd³ capacity; full first; 17 minutes between arrivals.
  • Quote B: 6 yd³ capacity; balanced; 28 minutes between arrivals.

Result:

Quote A delivers 16.25 yd³ and clears the site at minute 68 for $3,008.75. Quote B delivers 16.50 yd³ and clears at minute 84 for $2,934.50. B is $74.25 lower and has one minute of modeled access headroom.

Frequently Asked Questions

Does this estimate how much concrete my slab needs?

Start with the measured slab volume, including your chosen allowance. Use the linked Concrete Slab Calculator to estimate that entered volume.

Why does quote volume differ from my target?

An order can only include a whole number of the quoted volume increment. A balanced arrangement divides those increments as evenly as possible while keeping the same order total.

What if two trucks arrive at once?

The entered dispatch order breaks the tie. The second truck queues until the previous truck finishes closeout.

What does the included on-site time cover?

This planner counts from arrival to release. Written contracts can use different timing or allowances, so use this comparison only if it represents your quote.

Does a plan that fits the cutoff meet a concrete discharge specification?

The cutoff represents the access window you entered. Actual discharge specifications and acceptable delivery conditions need to be agreed with the concrete producer.