Production effectiveness

Compare mixed-product shift OEE

Only Plan B meets the entered OEE target.
Where each shift’s planned time went

Plan A

76.3889%

Below exact target

Fully productive
5,500 s
Stops
900 s
Speed loss
600 s
Reject loss
200 s

Availability 87.5000% · Performance 90.4762% · Equivalent-time quality 96.4912%

Inspect a segment in Plan A

Fast · 290 of 300 good

300 good required in this segment, with other segments fixed.

10 additional good pieces needed.

Plan B

77.7778%

Meets target

Fully productive
5,600 s
Stops
900 s
Speed loss
150 s
Reject loss
550 s

Availability 87.5000% · Performance 97.6190% · Equivalent-time quality 91.0569%

Inspect a segment in Plan B

Fast · 140 of 145 good

140 good required in this segment, with other segments fixed.

This segment has enough good pieces.

Shift records and target

Enter up to six rows per plan, separated by commas or tabs. Columns in order are Product, Planned minutes, Stopped minutes, Ideal seconds, Total, Good. Each row covers a separate part of a shift.

Review the production ledger and exact CSV
Production segments and time losses
SegmentPlannedRunIdeal productionFully productiveStopsSpeed lossReject loss
A1 · Fast3,600 s3,300 s3,000 s2,900 s300 s300 s100 s
A2 · Slow3,600 s3,000 s2,700 s2,600 s600 s300 s100 s
B1 · Fast1,800 s1,500 s1,450 s1,400 s300 s50 s50 s
B2 · Slow5,400 s4,800 s4,700 s4,200 s600 s100 s500 s

How to use this calculator

  1. Enter the shift OEE target and an example or recorded shift for each plan.
  2. For each segment, enter a product label, planned minutes, stopped minutes, ideal seconds per piece, total pieces and good pieces.
  3. Compare the time breakdown and select a segment to see how many good parts it needs to meet the target.
  4. Open the ledger and save the exact CSV for independent checking.

The Formula

The mathematical logic powering this calculation is:

For each segment, run time is planned time less stops. Ideal production time is total pieces times ideal cycle seconds, and fully productive time is good pieces times ideal cycle seconds. The three losses are stops, run time less ideal production time, and ideal production time less fully productive time.
Shift OEE is the sum of fully productive time divided by the sum of planned time. Availability is total run time divided by total planned time. Performance is total ideal production time divided by total run time. In this worksheet, equivalent-time quality is total fully productive time divided by total ideal production time. Those factors multiply to the direct ratio when their denominators exist. Simple averages of row OEE or quality by raw count can give different answers when products have different cycle times.
The target calculation holds other segments and the selected segment's total pieces fixed. Subtract the other segments' fully productive time from the time required for the target, then divide by this segment's ideal cycle time, rounding up to a whole good piece. A requirement above the total count cannot be met by improving quality alone in that segment.
Use disjoint segments from one production resource per plan, with the site’s consistently applied definitions of planned time, downtime and good counts. A row whose ideal production time exceeds logged run time is flagged. Remove overlap, correct timing, or check the ideal cycle before using the plan's OEE. This worksheet accepts up to six segments per plan.

Worked Example

If you input:

  • Plan A: 5,500 fully productive seconds in 120 planned minutes
  • Plan B: 5,600 fully productive seconds in 120 planned minutes
  • OEE target: 77.77%

Result:

Plan A achieves 76.3889% and Plan B achieves 77.7778%. Plan B meets 77.77%. At a 77.78% target, its second segment would need one additional good piece if the first stays fixed.

Frequently Asked Questions

Can I combine products with different ideal cycle times?

Yes. Use a separate segment per product or run. The worksheet adds their planned times and good production measured in ideal-cycle seconds.

Which stops belong in a segment?

Count time within that row's entered planned production window, using the same stop conventions in both plans.

Can I evaluate an idle shift?

Yes. A planned segment with zero pieces contributes zero fully productive time. The ledger still distinguishes recorded stops and the rest of the unproductive time.

Why is a shift flagged as inconsistent?

A recorded count implies more ideal production time than a segment's logged run time. Check the duration, included stops, count and ideal cycle before relying on the result.

How does the target account for reject reductions?

It holds the entered total counts and timing fixed, then varies good count for the selected segment. A segment cannot supply more good pieces than it produced.