OEE Calculator
See where production time goes. Compare production periods, inspect availability, performance and first-pass quality, and reconcile their combined OEE with a transparent loss breakdown.
See where production time goes.
Connect your production log to stops, speed and first-pass quality. Compare periods using one shared ideal cycle, with every minute accounted for.
Combined OEE
≈72.8175 %
Productive ideal time / total planned production time. Combined from underlying quantities.
First-pass good output
36700
Of 37500 units across 2 entered periods. Reworked units are excluded from first-pass good.
- Availability
- ≈91.0714 %
- Run time / planned production time
- Performance
- ≈81.6993 %
- Ideal total-output time / run time
- First-pass quality
- ≈97.8667 %
- First-pass good / total count
Shared production basis
Fastest ideal time for one counted unit: 0.000001–86,400 seconds. All periods must describe the same process and output basis. Convert batch or multicavity cycles to seconds per unit first.
Edit a production period
2 of 12 periods. Avoid overlapping or double-counted production.
Optional label, up to 60 characters. An empty label uses its period number.
Enter 0–1,000,000 minutes after excluding time with no intention to produce. Planned changeovers within production stay included.
Time stopped within planned production, including changeovers. Count each stop once; it cannot exceed planned time.
All produced units, including rejects. Enter a whole number from 0 to 1 billion, without separators.
Units accepted on their first pass, excluding rework. This cannot exceed the total count.
Follow the production time
All periods. Planned time steps down through stops, speed loss and reject-equivalent time to fully productive time. Speed and reject losses express equivalent time, not separately timed events.
Time (minutes)
- 1. Planned production840 minShare of planned time: 100 %
- 2. Stop time75 minShare of planned time: ≈8.92857 %
- 3. Speed loss140 minShare of planned time: ≈16.6667 %
- 4. Reject-equivalent time≈13.3333 minShare of planned time: ≈1.5873 %
- 5. Fully productive time≈611.667 minShare of planned time: ≈72.8175 %
All periods
Entered data reconciles
- OEE
- ≈72.8175 %
- Planned production
- 840 min
- Run time
- 765 min
- Productive equivalent
- ≈611.667 min
| Component | Minutes | Of planned |
|---|---|---|
| Stop time | 75 | ≈8.92857 % |
| Speed loss | 140 | ≈16.6667 % |
| Reject-equivalent time | ≈13.3333 | ≈1.5873 % |
| Fully productive time | ≈611.667 | ≈72.8175 % |
The components add to planned time. Reject and productive time are ideal-time equivalents. A negative speed loss signals inconsistent inputs and appears as an upward step.
- Availability
- ≈91.0714 %
- Run time / planned production time
- Performance
- ≈81.6993 %
- Ideal total-output time / run time
- First-pass quality
- ≈97.8667 %
- First-pass good / total count
Compare production periods
OEE on one percentage scale. All periods combines the underlying times and counts; it is not an average of the period scores. Choose a period below to inspect its time breakdown.
The common percentage scale is not a performance benchmark. Undefined values have no bar, rather than a zero score.
All periods uses summed times and counts. It is not the average of the bars. There is no universal target or grade applied here.
Complete period ledger
All entered periods stay represented. Scroll the table horizontally to inspect the factors; select a period to show its loss waterfall.
| Period | Planned min | Stopped min | Total | Good | Availability | Performance | Quality | OEE | Status |
|---|---|---|---|---|---|---|---|---|---|
| 420 | 45 | 18000 | 17700 | ≈89.2857 % | 80 % | ≈98.3333 % | ≈70.2381 % | Entered data reconciles | |
| 420 | 30 | 19500 | 19000 | ≈92.8571 % | ≈83.3333 % | ≈97.4359 % | ≈75.3968 % | Entered data reconciles | |
| All periods | 840 | 75 | 37500 | 36700 | ≈91.0714 % | ≈81.6993 % | ≈97.8667 % | ≈72.8175 % | Entered data reconciles |
Save or import production inputs
Complete report
Save every period, combined factor, signed loss, input assumption and plotted value in one CSV. The selected waterfall is included alongside the full comparison.
Complete report CSV
Convention and assumptions
Use comparable, non-overlapping production periods for one process and output basis. The ideal cycle is per counted unit. Exclude time without production intention before entering planned time; keep production changeovers in stops.
First-pass good excludes rework. Equivalent time is an accounting quantity based on the entered ideal cycle, not a measured chronology or a prediction of recoverable output. No universal target, cost or equipment recommendation is inferred.
- All periods describe the same equipment, process and product using one shared ideal time per counted output unit.
- Planned production time already excludes time with no intention to produce. Logged stops include planned changeovers and unplanned stops.
- Good count means first-pass acceptable output; units requiring rework are not first-pass good units.
- Speed and reject losses are equivalent time. Do not double-count logged stops in speed loss.
- Aggregate results sum underlying times and counts rather than averaging percentages. These are descriptive arithmetic results, not output or cost forecasts.
Decimal inputs are evaluated as exact fractions. Displayed decimals may be rounded and marked with ≈. A chart can make very small differences hard to distinguish; inspect the table and complete report for their numerical values.
How to use this calculator
- Enter Ideal cycle time (s/unit) for one equipment, process and output basis. Use seconds per counted unit, converting a batch or multicavity cycle yourself before entry. Keep this same basis for every period.
- Select a period and edit Period label, Planned production (min) and Stop time (min). Planned production already excludes time when production was not intended. Stop time includes breakdowns and changeovers within planned production; count each stop once.
- Enter Total count and First-pass good count. First-pass good excludes units that needed rework. Add up to 12 comparable periods, retaining each period's own times and counts rather than entering averaged percentages.
- Read the combined OEE, availability, performance and quality, then inspect an individual period. Correct malformed rows before using the combined result. A cycle inconsistency remains visible and must not be treated as a normal effectiveness assessment.
- Inspect the selected loss waterfall and period comparison. An upward speed-loss step represents negative inferred loss and inconsistent input assumptions. Undefined factors remain distinct from real zero values; exact quantities and the Complete OEE period ledger provide the underlying values.
- Choose Input format to stage a complete CSV or TSV plan, review the preview and apply it explicitly. Reusable input preserves unfinished drafts. Download a complete result report when all rows are numerically valid; inconsistent and no-planned-time results retain their statuses and undefined reasons in the report.
The Formula
The mathematical logic powering this calculation is:
Use one shared ideal cycle C in seconds per counted output unit. For each period, convert planned and stopped minutes to seconds: P = 60 × planned minutes, S = 60 × stop minutes, and run time R = P − S. With total count T and first-pass good count G, ideal total time N = C × T and productive equivalent time F = C × G.
Availability = R/P, performance = N/R, first-pass quality = G/T, and direct OEE = F/P. Multiply a defined ratio by 100 to express it as a percentage. Calculate combined ratios from summed times and counts, not averages of period percentages. When all denominators are positive, availability × performance × quality equals direct OEE.
The loss breakdown is stopped time S, signed speed loss R − N, reject-equivalent time N − F, and fully productive equivalent time F. Their exact sum is P. Equivalent time values describe accounting at the entered ideal rate, not measured time spent reworking individual units or a chronological stop log.
A zero denominator makes that factor unavailable, with its reason retained. Direct OEE can still be zero when planned time is positive and production is zero. If N exceeds R, negative speed loss and any defined ratios remain visible as inconsistent arithmetic. An inconsistent period continues to qualify the combined result even when aggregate performance is below 100%. Exact arithmetic is conditional on the entered values and does not validate their operational measurement.Worked Example
If you input:
- Ideal cycle time (s/unit): 1
- Period A — Planned production (min) / Stop time (min): 420 / 45
- Period A — Total count / First-pass good count: 18,000 / 17,700
- Period B — Planned production (min) / Stop time (min): 420 / 30
- Period B — Total count / First-pass good count: 19,500 / 19,000
Result:
The combined OEE is approximately 72.817460%, with availability 91.071429%, performance 81.699346% and first-pass quality 97.866667%. The 840 planned minutes reconcile to 75 stopped minutes, 140 speed-loss minutes, 13⅓ reject-equivalent minutes and 611⅔ fully productive equivalent minutes. The combined result uses 37,500 total units and 36,700 first-pass good units; it does not average the two period percentages.
Frequently Asked Questions
Which time belongs in planned production and stops?
Planned production is time when the process was intended to produce. Exclude intervals with no production intention before entering it. Within planned production, logged breakdowns and planned changeovers both count as stops. Do not remove a changeover merely because it was scheduled, and do not count the same interruption again as a separate loss. The tool accepts your classifications; it cannot infer intentions or detect overlapping period logs.
Does first-pass good count include repaired or reworked units?
No. First-pass good counts units accepted without needing rework. Total count includes the counted output on the same basis, and first-pass good cannot exceed it. The difference contributes reject-equivalent time at the entered ideal cycle, not measured rework duration. Later recovery of a unit does not retroactively make its first pass good. Use consistent counting rules across all periods so their combined quality ratio is meaningful.
How are several periods combined?
The calculator sums planned time, stopped time, total count and first-pass good count, then derives the combined factors from those totals using one shared ideal cycle. It does not take an unweighted average of period scores. A short period and a long period generally contribute differently. Use comparable periods of the same equipment, process and output basis; different products requiring different ideal cycle times need separate analyses in this version.
Why can performance exceed 100% or speed loss become negative?
If ideal cycle time multiplied by total count exceeds recorded run time, the entered assumptions contradict the stated ideal rate. Review cycle time, counts and period boundaries. The tool retains the signed arithmetic and marks the period inconsistent instead of clamping it to 100%. OEE below 100% does not resolve that contradiction. A slower period can mask it in the combined ratio, so the combined result still carries the individual period's issue.
What happens when planned time, run time or total count is zero?
Each factor keeps its own denominator rule: availability and direct OEE need positive planned time, performance needs positive run time, and quality needs positive total count. An unavailable factor is not displayed as zero or 100%. Positive planned time with no good output still gives direct OEE zero, even when the factor product is unavailable. Positive output with no run time remains explicitly inconsistent arithmetic, rather than disappearing from the plan.
What do the waterfall and comparison establish?
The waterfall reconciles planned time through run time and ideal total time to fully productive equivalent time. Its losses are accounting quantities, not a timeline of individual events. The comparison shows period OEE on a common scale without assigning an industry grade. These inputs do not separate all six underlying loss causes, calculate TEEP, diagnose equipment or promise that recovering a loss will generate additional output or profit.
What input limits and unfinished drafts are supported?
Use 1–12 periods, ideal cycle time from 0.000001 to 86,400 seconds per unit, times from zero to 1,000,000 minutes, and whole counts up to 1,000,000,000. Time and cycle atoms accept up to 12 significant digits and six effective decimal places. Blank or malformed numeric drafts remain editable. One invalid row preserves valid peers but blocks the combined result and complete report; a structurally valid reusable input can still preserve that unfinished plan.
Similar Calculators
Milling Speeds and Feeds Calculator
Calculate milling RPM, cutting speed and table feed from your cutting data. Inspect radial chip thinning and compare explicit machine ceilings.
Time Tracking Calculator
Track total worked time across multiple shifts and break periods with dynamic start and end inputs.
Break-Even Calculator
Find the break-even point for your business — how many units you must sell to cover all costs.