Production Cycle Time & Batch Capacity Planner

Compare two production plans with one to six stations. Enter startup readiness, repeated setup, per-unit work, lot size and available lots. Follow each complete lot through a buffered line or a one-lot-at-a-time rule. The timelines and exact ledger show completed units, remaining work and the extra time needed to meet the entered demand.

Production batches

Compare lot flow and shift output

Completed units and demand

Plan A · Larger lots

40 units completed

5 whole lots · 7 lots in process

8 units short

3 min more to meet demand

First finished lot
33 min
Repeat interval
14 min/lot
Next outside shift
103 min
Longest station time
14 min/lot

Plan B · Smaller lots

48 units completed

12 whole lots · 8 lots in process

Meets demand exactly

Demand fits the shift

First finished lot
19 min
Repeat interval
7 min/lot
Next outside shift
103 min
Longest station time
7 min/lot

Plan A 40 units completed. Plan B 48 units completed

In-shift station timelines

  • Setup
  • Processing
  • Runs past cutoff
Plan A · Larger lots

Buffered line

Cut96 min busy

Form · Bottleneck90 min busy

Pack51 min busy

0 min50 min100 min cutoff
Plan B · Smaller lots

Buffered line

Cut98 min busy

Form · Bottleneck93 min busy

Pack62 min busy

0 min50 min100 min cutoff

Each block continues one lot at a station. Empty time can reflect readiness or waiting for the preceding station. Inspect exact minutes in the ledger.

Shift and station inputs

A buffered line allows several lots at independent stations with space between them. One lot active holds the next lot until the current one leaves the final station.

Edit station sequence

Enter stations in transfer order. Ready time is the first minute the station can begin. Setup repeats at each lot.

Station 1
Station 2
Station 3

Exact production timing ledger

Plan A · Larger lots. Entries after the cutoff show the projection if the modeled window were extended.

Projected start and finish minutes for each lot, plus status against the entered cutoff
LotLine finishAt cutoffCutFormPack
Lot 133 minComplete2 min–10 minSetup ends 4 min10 min–24 minSetup ends 12 min24 min–33 minSetup ends 25 min
Lot 247 minComplete10 min–18 minSetup ends 12 min24 min–38 minSetup ends 26 min38 min–47 minSetup ends 39 min
Lot 361 minComplete18 min–26 minSetup ends 20 min38 min–52 minSetup ends 40 min52 min–61 minSetup ends 53 min
Lot 475 minComplete26 min–34 minSetup ends 28 min52 min–66 minSetup ends 54 min66 min–75 minSetup ends 67 min
Lot 589 minComplete34 min–42 minSetup ends 36 min66 min–80 minSetup ends 68 min80 min–89 minSetup ends 81 min
Lot 6103 minIn process42 min–50 minSetup ends 44 min80 min–94 minSetup ends 82 min94 min–103 minSetup ends 95 min
Lot 7117 minIn process50 min–58 minSetup ends 52 min94 min–108 minSetup ends 96 min108 min–117 minSetup ends 109 min
Lot 8131 minIn process58 min–66 minSetup ends 60 min108 min–122 minSetup ends 110 min122 min–131 minSetup ends 123 min
Lot 9145 minIn process66 min–74 minSetup ends 68 min122 min–136 minSetup ends 124 min136 min–145 minSetup ends 137 min
Lot 10159 minIn process74 min–82 minSetup ends 76 min136 min–150 minSetup ends 138 min150 min–159 minSetup ends 151 min
Lot 11173 minIn process82 min–90 minSetup ends 84 min150 min–164 minSetup ends 152 min164 min–173 minSetup ends 165 min
Lot 12187 minIn process90 min–98 minSetup ends 92 min164 min–178 minSetup ends 166 min178 min–187 minSetup ends 179 min
Download production CSV
Open selectable production CSV

How to use this calculator

  1. Enter continuous working time and demand for the same window. Select a plan and enter the units per lot and available whole lots.
  2. Choose a buffered line or one lot active. Add stations in the transfer order and enter each ready minute, setup per lot and work per unit.
  3. Compare whole-lot completions and select the station to adjust if a planned operation is taking longer. The longest stations are labeled on the timeline.
  4. Review the minute or extra time needed to cover demand. Confirm whether the available lot limit rules out meeting the target.
  5. Use the ledger and download the complete schedule for both plans.

The Formula

The mathematical logic powering this calculation is:

Enter a contiguous working window and two serial station sequences. Each station is available from an entered ready minute. Its operation duration equals fixed setup per lot plus work per unit multiplied by the plan’s lot size. Setup comes first and consumes the station for the current lot. The ready time is a one-time availability mark. Every station has one processing slot, and whole lots proceed in the declared order with no move time.

In the buffered mode, each task starts when both the lot and that station are available. Take the maximum of the preceding station’s finish for this lot and the current station’s previous lot finish, using the station’s ready minute before its first lot. Add the station duration to get finish. Unfinished material can wait between stations with no buffer capacity limit. The one-lot-active mode additionally requires the previous lot to leave the last station before the next begins the first. No worker is assigned by the model. The modes are alternative deterministic release conditions.

A first lot’s full-line finish includes the effect of startup readiness. After startup, the mathematical repeat interval for a buffered line is the longest per-lot station duration. In one-lot-active mode it is the sum of the station durations. The shift result uses the complete finite schedule. Count units only for lots that finish the final station at or before the shift cutoff. An unfinished lot counts as in process only if its first task started before the cutoff. Each station's busy minutes are the overlap of its exact tasks with the entered window.

Divide demand by units per lot and round upward to locate the first lot that meets demand. When it exists within the supplied release cap, the additional working time is its exact finishing minute minus the shift, floored at zero. If the available whole lots cannot supply the required units, show that material shortfall separately. A projected finish outside the shift assumes the same deterministic availability and workload continue. Demand is a target for comparison; it does not stop the release of later available lots.

Use 0–10,080 working minutes for the shift and ready offsets, 0–1,000 minutes each for setup or work per unit and up to three decimal places. Each repeated operation needs a positive total duration. Enter 1–6 stations, 1–10,000 units per lot, 1–120 available lots and 0–1,000,000 units of demand. Exact thousandths decide timeline boundaries. No breaks during the window, unplanned downtime, random variation, multiple parallel machines at one station, order changes, shared worker schedules, partial transfers, rejects, rework or carry-in inventory are modeled.

Worked Example

If you input:

  • Shift and demand: 100 min available, 48 units demanded.
  • Plan A: Buffered, eight units per lot, 12 available lots. Cut has 2 min setup and 0.75 min/unit, Form 2 and 1.5, Pack 1 and 1.
  • Plan B: Buffered, four units per lot, 20 available lots. Form work is 1.25 min/unit. Other setup and per-unit values follow Plan A.
  • Station readiness: Cut is ready at minute 2, Form at 0 and Pack at 5 in both plans.

Result:

Plan A first finishes at minute 33. Five lots complete in the shift, giving 40 units and seven unfinished lots that had started. It needs 3 more minutes for the sixth lot to make demand. Plan B first finishes at minute 19, and 12 lots give 48 units at minute 96 with eight unfinished lots in process.

Frequently Asked Questions

How does this use production cycle time?

The worksheet calculates a planned duration for each station and repeats the station sequence across the entered lots. A buffered line’s repeat interval comes from its longest station once startup effects have passed.

Does every completed station add produced units?

Units are credited only when the whole lot finishes the last station. The ledger indicates started lots that remain unfinished at the cutoff.

Is ready time the same as setup?

Ready time says when the station first becomes available. Setup per lot repeats for every lot and occupies the station before the entered per-unit work.

How is one lot active different from a buffered line?

With one lot active the first station waits for the previous lot to leave the line before starting the next. A buffered line allows different lots to occupy different available stations at once.

Why are there tasks beyond the shift in the ledger?

The worksheet projects the declared available lots so it can show the time needed to meet demand or identify a material limit. Each row marks its status relative to the entered cutoff.

Can I make a larger shift cover any demand?

A larger uninterrupted window helps only when enough whole lots are available. If the authored release cap is too small, the calculation reports the units missing from that cap.

How does this relate to takt time or OEE?

Takt time divides available time by customer demand and expresses a target pace. OEE accounts for observed production losses. This worksheet schedules a specific planned sequence and counts its completed lots.