Production Cycle Time & Batch Capacity Planner
Compare two production plans with one to six stations. Enter startup readiness, repeated setup, per-unit work, lot size and available lots. Follow each complete lot through a buffered line or a one-lot-at-a-time rule. The timelines and exact ledger show completed units, remaining work and the extra time needed to meet the entered demand.
Compare lot flow and shift output
Enter two station sequences. Inspect each lot’s start and finish, time spent on setup and whether whole-lot output covers demand.
Completed units and demand
Plan A · Larger lots
40 units completed
5 whole lots · 7 lots in process
8 units short
3 min more to meet demand
- First finished lot
- 33 min
- Repeat interval
- 14 min/lot
- Next outside shift
- 103 min
- Longest station time
- 14 min/lot
Plan B · Smaller lots
48 units completed
12 whole lots · 8 lots in process
Meets demand exactly
Demand fits the shift
- First finished lot
- 19 min
- Repeat interval
- 7 min/lot
- Next outside shift
- 103 min
- Longest station time
- 7 min/lot
Plan A 40 units completed. Plan B 48 units completed
In-shift station timelines
- Setup
- Processing
- Runs past cutoff
Buffered line
Cut96 min busy
Form · Bottleneck90 min busy
Pack51 min busy
Buffered line
Cut98 min busy
Form · Bottleneck93 min busy
Pack62 min busy
Each block continues one lot at a station. Empty time can reflect readiness or waiting for the preceding station. Inspect exact minutes in the ledger.
Shift and station inputs
A buffered line allows several lots at independent stations with space between them. One lot active holds the next lot until the current one leaves the final station.
Edit station sequence
Enter stations in transfer order. Ready time is the first minute the station can begin. Setup repeats at each lot.
Exact production timing ledger
Plan A · Larger lots. Entries after the cutoff show the projection if the modeled window were extended.
| Lot | Line finish | At cutoff | Cut | Form | Pack |
|---|---|---|---|---|---|
| Lot 1 | 33 min | Complete | 2 min–10 minSetup ends 4 min | 10 min–24 minSetup ends 12 min | 24 min–33 minSetup ends 25 min |
| Lot 2 | 47 min | Complete | 10 min–18 minSetup ends 12 min | 24 min–38 minSetup ends 26 min | 38 min–47 minSetup ends 39 min |
| Lot 3 | 61 min | Complete | 18 min–26 minSetup ends 20 min | 38 min–52 minSetup ends 40 min | 52 min–61 minSetup ends 53 min |
| Lot 4 | 75 min | Complete | 26 min–34 minSetup ends 28 min | 52 min–66 minSetup ends 54 min | 66 min–75 minSetup ends 67 min |
| Lot 5 | 89 min | Complete | 34 min–42 minSetup ends 36 min | 66 min–80 minSetup ends 68 min | 80 min–89 minSetup ends 81 min |
| Lot 6 | 103 min | In process | 42 min–50 minSetup ends 44 min | 80 min–94 minSetup ends 82 min | 94 min–103 minSetup ends 95 min |
| Lot 7 | 117 min | In process | 50 min–58 minSetup ends 52 min | 94 min–108 minSetup ends 96 min | 108 min–117 minSetup ends 109 min |
| Lot 8 | 131 min | In process | 58 min–66 minSetup ends 60 min | 108 min–122 minSetup ends 110 min | 122 min–131 minSetup ends 123 min |
| Lot 9 | 145 min | In process | 66 min–74 minSetup ends 68 min | 122 min–136 minSetup ends 124 min | 136 min–145 minSetup ends 137 min |
| Lot 10 | 159 min | In process | 74 min–82 minSetup ends 76 min | 136 min–150 minSetup ends 138 min | 150 min–159 minSetup ends 151 min |
| Lot 11 | 173 min | In process | 82 min–90 minSetup ends 84 min | 150 min–164 minSetup ends 152 min | 164 min–173 minSetup ends 165 min |
| Lot 12 | 187 min | In process | 90 min–98 minSetup ends 92 min | 164 min–178 minSetup ends 166 min | 178 min–187 minSetup ends 179 min |
Open selectable production CSV
How to use this calculator
- Enter continuous working time and demand for the same window. Select a plan and enter the units per lot and available whole lots.
- Choose a buffered line or one lot active. Add stations in the transfer order and enter each ready minute, setup per lot and work per unit.
- Compare whole-lot completions and select the station to adjust if a planned operation is taking longer. The longest stations are labeled on the timeline.
- Review the minute or extra time needed to cover demand. Confirm whether the available lot limit rules out meeting the target.
- Use the ledger and download the complete schedule for both plans.
The Formula
The mathematical logic powering this calculation is:
Enter a contiguous working window and two serial station sequences. Each station is available from an entered ready minute. Its operation duration equals fixed setup per lot plus work per unit multiplied by the plan’s lot size. Setup comes first and consumes the station for the current lot. The ready time is a one-time availability mark. Every station has one processing slot, and whole lots proceed in the declared order with no move time.
In the buffered mode, each task starts when both the lot and that station are available. Take the maximum of the preceding station’s finish for this lot and the current station’s previous lot finish, using the station’s ready minute before its first lot. Add the station duration to get finish. Unfinished material can wait between stations with no buffer capacity limit. The one-lot-active mode additionally requires the previous lot to leave the last station before the next begins the first. No worker is assigned by the model. The modes are alternative deterministic release conditions.
A first lot’s full-line finish includes the effect of startup readiness. After startup, the mathematical repeat interval for a buffered line is the longest per-lot station duration. In one-lot-active mode it is the sum of the station durations. The shift result uses the complete finite schedule. Count units only for lots that finish the final station at or before the shift cutoff. An unfinished lot counts as in process only if its first task started before the cutoff. Each station's busy minutes are the overlap of its exact tasks with the entered window.
Divide demand by units per lot and round upward to locate the first lot that meets demand. When it exists within the supplied release cap, the additional working time is its exact finishing minute minus the shift, floored at zero. If the available whole lots cannot supply the required units, show that material shortfall separately. A projected finish outside the shift assumes the same deterministic availability and workload continue. Demand is a target for comparison; it does not stop the release of later available lots.
Use 0–10,080 working minutes for the shift and ready offsets, 0–1,000 minutes each for setup or work per unit and up to three decimal places. Each repeated operation needs a positive total duration. Enter 1–6 stations, 1–10,000 units per lot, 1–120 available lots and 0–1,000,000 units of demand. Exact thousandths decide timeline boundaries. No breaks during the window, unplanned downtime, random variation, multiple parallel machines at one station, order changes, shared worker schedules, partial transfers, rejects, rework or carry-in inventory are modeled.Method sources
Worked Example
If you input:
- Shift and demand: 100 min available, 48 units demanded.
- Plan A: Buffered, eight units per lot, 12 available lots. Cut has 2 min setup and 0.75 min/unit, Form 2 and 1.5, Pack 1 and 1.
- Plan B: Buffered, four units per lot, 20 available lots. Form work is 1.25 min/unit. Other setup and per-unit values follow Plan A.
- Station readiness: Cut is ready at minute 2, Form at 0 and Pack at 5 in both plans.
Result:
Plan A first finishes at minute 33. Five lots complete in the shift, giving 40 units and seven unfinished lots that had started. It needs 3 more minutes for the sixth lot to make demand. Plan B first finishes at minute 19, and 12 lots give 48 units at minute 96 with eight unfinished lots in process.
Frequently Asked Questions
How does this use production cycle time?
The worksheet calculates a planned duration for each station and repeats the station sequence across the entered lots. A buffered line’s repeat interval comes from its longest station once startup effects have passed.
Does every completed station add produced units?
Units are credited only when the whole lot finishes the last station. The ledger indicates started lots that remain unfinished at the cutoff.
Is ready time the same as setup?
Ready time says when the station first becomes available. Setup per lot repeats for every lot and occupies the station before the entered per-unit work.
How is one lot active different from a buffered line?
With one lot active the first station waits for the previous lot to leave the line before starting the next. A buffered line allows different lots to occupy different available stations at once.
Why are there tasks beyond the shift in the ledger?
The worksheet projects the declared available lots so it can show the time needed to meet demand or identify a material limit. Each row marks its status relative to the entered cutoff.
Can I make a larger shift cover any demand?
A larger uninterrupted window helps only when enough whole lots are available. If the authored release cap is too small, the calculation reports the units missing from that cap.
How does this relate to takt time or OEE?
Takt time divides available time by customer demand and expresses a target pace. OEE accounts for observed production losses. This worksheet schedules a specific planned sequence and counts its completed lots.
Similar Calculators
OEE Calculator
Calculate overall equipment effectiveness across production periods. Inspect availability, performance, first-pass quality and equivalent time losses.
Critical Path Calculator
Plan finish-to-start dependencies, find critical chains and compare a changed activity duration. Explore Gantt timing, waiting lags and shared float.
Process Capability & Cpk Calculator
Compare Cp, Cpk and Cpm for two processes. Enter sample readings or summaries, set specification limits and see which change would meet your index goal.
Marginal Cost & Production Tier Calculator
Calculate the cost of making one more unit or moving to a new capacity tier. Compare two production quantities after step charges, sales and inventory costs.
Labor Productivity & Work Mix Calculator
Compare labor productivity across two periods. Weight completed work by standard minutes to account for job mix, then examine direct time and execution separately.
Two-Stage Job Sequencing Calculator & Johnson’s Rule
Find the fastest order for jobs through two shared stations. Compare finish time, idle gaps and completions by a cutoff on one timeline.
Assembly Line Station Balance Calculator
Assign tasks to the fewest feasible stations at two cycle times. Account for predecessors and find the exact fastest cycle for your station budget.