Earned Value Work Package & Milestone Calculator
Enter authorized work-package budgets and current actual cost. Assign each package’s budget to weighted milestones, then compare planned and earned credit at one status point. Trace the project rollup to the contributing packages.
Roll earned value up from work packages
Calculate the budget at completion and trace planned value, earned value and variance to their underlying milestones.
Edit budgets and milestone credits
For the same status point, paste package, budget and actual cost. In the milestone table, paste package, milestone, weight, planned percent and earned percent.
Use one currency throughout and matching package labels. Each package’s milestone weights must total exactly 100%.
Budget at completion
200,000
Planned value
122,000
Earned value
90,000
Actual cost
71,000
Budget-weighted progress 45% earned and 61% planned.
- Cost variance (EV − AC)
- 19,000
- Schedule variance (EV − PV)
- −32,000
Planned and earned value by package
Compare planned and earned milestone credit. The numbered rows follow the order of the work packages you entered.
- Planned value
- Earned value
1 · Design
- Budget
- 60,000
- Planned
- 51,000
- Earned
- 42,000
- Actual
- 33,000
- Cost variance
- 9,000
- Schedule variance
- −9,000
Review milestone credits and export CSV
| Package | Milestone | Weight % | Allocated | Planned | Earned |
|---|---|---|---|---|---|
| Design | Draft | 40 | 24,000 | 24,000 | 24,000 |
| Design | Review | 60 | 36,000 | 27,000 | 18,000 |
| Build | Prototype | 25 | 30,000 | 30,000 | 30,000 |
| Build | Assembly | 75 | 90,000 | 36,000 | 18,000 |
| Test | Validation | 100 | 20,000 | 5,000 | 0 |
How to use this calculator
- Paste package label, authorized budget and actual cost for each work package.
- Paste milestone rows with package label, milestone label, weight, planned percent and earned percent. Use matching package labels and total each package’s weights to 100%.
- Read the project BAC, PV, EV and AC. Switch between the work and variance charts, and inspect an individual package.
- Open the milestone ledger to review credits and export exact values for your project reporting.
The Formula
The mathematical logic powering this calculation is:
For package budget B and milestone weight w%, allocate B × w/100. If planned milestone credit is p% and earned credit is e%, planned value is B × w × p/10,000 and earned value is B × w × e/10,000. Milestone weights must sum to 100% within each package. Credit is the stated measure of work at the selected status point.
Sum package budgets for budget at completion (BAC), milestone planned and earned amounts for total planned value (PV) and earned value (EV), and package actual costs for AC. Cost variance is EV − AC and schedule variance is EV − PV. Schedule variance is in budget units. Budget-weighted earned progress is EV/BAC and budget-weighted planned progress is PV/BAC.
Enter 1–8 work packages and 1–40 milestones. Package budgets must be positive and actual costs nonnegative, each through 1 billion in one currency with up to two decimals. Weights are positive, while planned and earned percentages range from zero through 100. Percentages accept up to six decimals. Matching package labels preserve their case. The rollup describes the supplied authorized work and its measured credit at a single status point. Exact rational calculations precede display rounding.Worked Example
If you input:
- Package budgets: Design 60,000, Build 120,000, Test 20,000
- Entered actual cost: 33,000, 38,000, 0
- Milestones: Five weighted milestones
Result:
The budget at completion is 200,000. Planned value is 122,000, earned value 90,000 and actual cost 71,000. Earned progress is 45%. The favorable cost variance is 19,000 and the schedule variance is −32,000 in budget units.
Frequently Asked Questions
How do I calculate budget at completion from work packages?
Sum the authorized budgets of the included work packages. Use the same currency and scope baseline for the current status.
What are weighted milestones?
They assign each milestone an agreed share of a work package’s budget. If the approved credit method gives partial progress, multiply that share by the credited percentage.
What does a positive cost variance mean when earned value is below plan?
The budgeted value of work accomplished exceeds its actual cost, while the work accomplished falls short of its planned budgeted value. The two variances measure different comparisons.
Why does a smaller package count less toward total progress?
Earned progress weights every package by its authorized budget. A large package accounts for a larger portion of overall budgeted work.
How do I use a milestone that only earns credit when complete?
Use zero or 100 for the earned percent according to whether the milestone meets its agreed completion criteria.
Similar Calculators
Earned Value Calculator
Compare planned value, earned value and actual cost. Track project history, inspect CPI and SPI, and compare completion-cost forecasts with your budget.
Critical Path Calculator
Plan finish-to-start dependencies, find critical chains and compare a changed activity duration. Explore Gantt timing, waiting lags and shared float.
Project Payback & Cash Recovery Planner
Compare two projects using dated cash flows, nominal and discounted payback, sustained recovery, and peak funding needs.
Budget at Completion Change Log Calculator
Reconcile budget at completion and management reserve as of a reporting date. Track authorized scope changes, reserve transfers and budget-ceiling headroom.