Budget at Completion Change Log Calculator
Start from your approved opening budget at completion and management reserve. Enter effective dates from the change log, keep pending requests visible, and see which changes move the total budget or reallocate it internally.
Reconcile your budget at completion
Apply authorized changes by effective date and compare the closing budget with your ceiling.
Bars follow effective order. The dashed line marks the entered ceiling.
- BAC
- Management reserve
- Ceiling $140,000.00
MR-02 · 2026-01-31
- Budget at completion
- $134,000.00
- Management reserve
- $6,000.00
- Tracked budget
- $140,000.00
Review the change ledger and exact CSV
| Reference | Effective date | State | BAC change | Reserve change | BAC after | Reserve after |
|---|---|---|---|---|---|---|
| CO-17 | 2026-01-10 | Applied | +$8,000.00 | $0.00 | $128,000.00 | $12,000.00 |
| MR-02 | 2026-01-31 | Applied | +$6,000.00 | -$6,000.00 | $134,000.00 | $6,000.00 |
| CO-20 | 2026-02-12 | Pending approval | -$4,000.00 | $0.00 | — | — |
| CO-22 | 2026-02-16 | Later effective date | +$1.00 | $0.00 | — | — |
How to use this calculator
- Enter the opening date, reporting date, approved BAC, management reserve and the ceiling you want to compare.
- Record each change’s reference, effective date, amount, approval and type. Order same-day changes as they should be applied.
- Read the closing BAC and reserve, inspect which changes were applied, and investigate any held rows.
- Download the exact ledger with the closing balances and headroom.
The Formula
The mathematical logic powering this calculation is:
Enter the opening budget at completion (BAC) and separately controlled management reserve. The tracked budget is their sum for the scope in this ledger. Management reserve enters BAC only when an authorized transfer allocates it to work.
Apply approved records dated on or before the as-of date, ordered by effective date. Use entered row order for ties. An authorized scope addition or reduction changes BAC and the tracked budget by that amount. A release increases BAC and reduces management reserve equally. A return to reserve decreases BAC and increases reserve equally. An opening-day change is applied after the opening balances.
A pending record remains outside the balances. An approved record with a later effective date stays visible for later reconciliation. If an eligible row would make BAC or reserve negative, retain the confirmed prefix and hold later eligible rows. Then the closing balance and ceiling comparison require reconciliation.
Headroom equals your entered ceiling minus the reconciled tracked budget. Exact zero means the ceiling is met. Amounts use exact US cents, with up to 15 records and USD 10 billion per input. The calendar accepts dates from 1900 through 2200. Reports cover the submitted ledger only. Contract pricing and fee, authorization decisions, changes to earned value and the cost to complete belong to their own records.Worked Example
If you input:
- Opening budgets: USD 120,000 BAC and USD 12,000 reserve
- Entered ceiling: USD 140,000
- Applicable records: USD 8,000 additional scope and USD 6,000 reserve release
- Reporting dates: February 15 and 16, 2026
Result:
On February 15, BAC is USD 134,000 and reserve is USD 6,000. Their total meets the USD 140,000 ceiling exactly. On February 16, an additional approved USD 1 increases the tracked budget above the ceiling.
Frequently Asked Questions
What is the difference between BAC and management reserve?
BAC is the authorized budget assigned to the work. Management reserve is held outside that baseline until an eligible release allocates it.
What happens when a transfer is dated on the reporting date?
The comparison includes approved transfers dated exactly on the reporting date. Same-day changes follow the entered order.
Does a reserve release increase the total tracked budget?
An approved release moves the same amount from management reserve to BAC. Their sum stays the same.
Why might a later approved change be held?
An earlier record would create a negative balance. Resolve that record to establish a consistent closing balance for later changes.
How do I move an already authorized budget among work packages?
A transfer from one work package to another can change package budgets without changing total BAC. Use the work-package worksheet to reconcile those amounts.
Similar Calculators
Earned Value Work Package & Milestone Calculator
Roll up budget at completion, planned value and earned value from work packages and weighted milestones. Inspect both cost and schedule variance.
Earned Value Calculator
Compare planned value, earned value and actual cost. Track project history, inspect CPI and SPI, and compare completion-cost forecasts with your budget.
Critical Path Calculator
Plan finish-to-start dependencies, find critical chains and compare a changed activity duration. Explore Gantt timing, waiting lags and shared float.
