Earned Value Calculator

See how completed work and actual spending compare with your project plan. Enter a snapshot or a reporting history, then compare explicit assumptions for the cost to finish against your approved budget.

Project review

See where the project stands. Compare the cost to finish.

Each mode keeps its own plan. All amounts in a plan use the same denomination; changing it relabels values without converting currency.

Try an example

Use the approved performance measurement baseline, excluding management reserve. Keep the same comparable baseline across history.

Amounts: 0–1e12, at most two effective decimal places; BAC must be positive. Decimal or scientific notation is accepted, without currency symbols or grouping commas.

Budgeted value of work planned by this observation.

Budgeted value of completed work. Spending alone does not establish progress.

Cost incurred for the work, which is not necessarily cash already paid.

Remaining-cost estimate and target

As of: Current snapshot

Estimated total cost (EAC)

125,000.00 USD

Current cost efficiency continues. Forecast is over BAC under this assumption.

Remaining cost (ETC)

80,000.00 USD

Variance at completion (VAC)

-25,000.00 USD

Cost performance (CPI)

≈ 0.8

Budgeted work earned per unit of incurred cost.

Schedule performance (SPI)

≈ 0.9

Budgeted work earned relative to planned work; not days ahead or late.

Cost variance (CV)

-9,000.00 USD

Incurred cost is greater than earned value.

Monetary schedule variance (SV)

-4,000.00 USD

Earned value minus planned value, in budget units.

Budgeted work complete
36%
Budgeted work planned
40%
Budget spent
45%

Completed work and spending are different measures. BAC: 100,000.00 USD.

Budgeted work remaining: 64,000.00 USD.

Current snapshot. Estimated total cost 125,000.00 USD. Complete export available.

Planned work, completed work and cost

One common scale: 0 to 100,000.00 USD. BAC is the approved work budget.

Planned value40,000.00 USD
Planned value: 40,000.00 USD. Full scale 100,000.00 USD.
Earned value36,000.00 USD
Earned value: 36,000.00 USD. Full scale 100,000.00 USD.
Actual cost45,000.00 USD
Actual cost: 45,000.00 USD. Full scale 100,000.00 USD.
Budget at completion100,000.00 USD
Budget at completion: 100,000.00 USD. Full scale 100,000.00 USD.

Compare assumptions for the cost to finish

Solid blue is actual cost incurred; dashed green is estimated remaining cost. The vertical reference is BAC. Every row shares a scale ending at ≈ 133,888.89 USD. These scenarios are not a confidence interval.

Remaining work at budgeted cost

Remaining budgeted work costs one unit for each unit of its budgeted value.

Remaining work at budgeted cost: 109,000.00 USD total; 45,000.00 USD actual and 64,000.00 USD remaining. BAC 100,000.00 USD.
Total cost
109,000.00 USD
Remaining cost
64,000.00 USD
Variance against BAC
-9,000.00 USD · over

Current cost efficiency continues · selected

The selected observation's cumulative CPI applies to remaining budgeted work.

Current cost efficiency continues: 125,000.00 USD total; 45,000.00 USD actual and 80,000.00 USD remaining. BAC 100,000.00 USD.
Total cost
125,000.00 USD
Remaining cost
80,000.00 USD
Variance against BAC
-25,000.00 USD · over

Cost and progress efficiency continue

The product of the selected cumulative CPI and SPI applies to remaining budgeted work. This is a cost scenario, not a finish-date forecast.

Cost and progress efficiency continue: ≈ 133,888.89 USD total; 45,000.00 USD actual and ≈ 88,888.89 USD remaining. BAC 100,000.00 USD.
Total cost
≈ 133,888.89 USD
Remaining cost
≈ 88,888.89 USD
Variance against BAC
≈ -33,888.89 USD · over

Entered remaining cost

Add the separately entered estimate to complete, including any explicit closeout cost.

Unavailable: Enable and enter a remaining-cost estimate to compare this scenario.

Required efficiency for the remaining work

Meet the original budget

Final-cost target: 100,000.00 USD

≈ 1.16364

Budgeted work earned per unit of remaining cost allowance.

Remaining allowance: 55,000.00 USD. Actual cost is under this target.

Required efficiency is higher than the current CPI. Exact difference: 4/11 . This comparison does not establish feasibility.

Enable a custom final-cost target above to compare a second remaining allowance. The original budget remains the baseline.

Project status and completion forecasts

The complete export includes both exact and approximate quantities, all entered observations, selection and assumptions.

View status and exact quantities
Current snapshot: status in USD
QuantityDisplayExact value and unit
BAC100,000.00 USD100000 USD
PV40,000.00 USD40000 USD
EV36,000.00 USD36000 USD
AC45,000.00 USD45000 USD
CV-9,000.00 USD-9000 USD
SV-4,000.00 USD-4000 USD
Budgeted work remaining64,000.00 USD64000 USD
Budgeted percent complete36%36 %
Percent planned40%40 %
Percent spent45%45 %
CPI0.84/5
SPI0.99/10
View cumulative observations and corrections

Amounts below are exact denomination values. Deltas compare adjacent supplied observations; the first has no known preceding observation. Decreases can reflect corrections and do not determine period efficiency.

Cumulative observations in entered order (USD)
ObservationPVEVACChange in PVChange in EVChange in ACReview
1. Current snapshot · selected40000 USD36000 USD45000 USDNo preceding observationNo preceding observationNo preceding observationNo decrease detected
View exact completion forecasts
Forecasts for Current snapshot; exact amounts in USD
AssumptionEACETCVACState
Remaining work at budgeted cost109000 USD64000 USD-9000 USDover BAC
Current cost efficiency continues125000 USD80000 USD-25000 USDover BAC
Cost and progress efficiency continue1205000/9 USD800000/9 USD-305000/9 USDover BAC
Entered remaining costEnable and enter a remaining-cost estimate to compare this scenario.
Selectable CSV text
Method, assumptions and sources

PV is planned budgeted work, EV is completed budgeted work, and AC is incurred cost. BAC is the approved work budget, excluding management reserve. All share one denomination and a comparable baseline. This planner does not infer progress from spending or manage changes to the baseline.

CV = EV − AC; SV = EV − PV; CPI = EV / AC; SPI = EV / PV
WR = BAC − EV; EAC = AC + ETC; VAC = BAC − EAC
ETC = WR, WR / CPI, WR / (CPI × SPI), or your entered estimate
TCPI = WR / (target − AC), when positive work and allowance remain

Zero denominators give unavailable indices. Positive remaining work needs positive defined efficiency for the CPI scenarios. When all budgeted work is earned, the first three forecasts equal actual cost; manual remaining cost can still include closeout costs. Monetary schedule variance and SPI do not establish days of delay, critical-path impact or a finish date. The scenario spread is not a probability interval.

Authored amounts use exact cents and derived values use exact fractions. Displays may be rounded; full fractions are in the ledger and CSV. A positive chart fraction below 0.000001 of its scale uses a limit marker rather than an ordinary zero. History decreases are flagged, not silently discarded. First-row deltas are unavailable without an earlier observation.

The input limits, correction flags and comparison states are this tool’s conventions. A calculated scenario is not an accounting audit, an EVMS certification or a guarantee of project performance.

How to use this calculator

  1. Choose Snapshot or Period history and a display denomination. Enter the approved Budget at completion (BAC); the calculator does not infer this baseline from spending. Changing USD, EUR, GBP or neutral units relabels amounts without converting currency.
  2. Enter Planned value (PV), Earned value (EV) and Actual cost (AC). For Period history, add ordered cumulative reporting observations or apply a complete CSV/TSV import, then choose the As-of observation. Cumulative decreases are allowed and flagged for review.
  3. Compare cost variance, monetary schedule variance, CPI and SPI. Keep budgeted percent complete separate from planned work and spending. An unavailable index has a specific reason; it is not replaced by zero or infinity.
  4. Choose a completion forecast: remaining work at budgeted rate, continuing CPI, continuing CPI × SPI, or an enabled entered remaining cost. Compare the assumptions and the resulting total cost, remaining cost and variance against BAC.
  5. Optionally enter a different final-cost target to compare required future efficiency. Correct or disable invalid enabled optional values before exporting. Inspect the selected status, history and forecast ledger, then request the CSV download or use the identical selectable text.

The Formula

The mathematical logic powering this calculation is:

BAC is the entered approved budget at completion. PV is the budgeted value of work planned by the selected observation; EV is the budgeted value of work actually completed; AC is the actual cost incurred. Amounts share one denomination.
CV = EV − AC; SV = EV − PV. Both variances are monetary. CPI = EV / AC when AC > 0; SPI = EV / PV when PV > 0. A zero denominator makes that index unavailable.
Budgeted work remaining WR = BAC − EV. Percent complete = 100 × EV / BAC; percent planned = 100 × PV / BAC; percent spent = 100 × AC / BAC. These are different quantities.
Remaining work at budgeted rate: EAC = AC + WR. Continuing current CPI: EAC = AC + WR / CPI. Continuing CPI × SPI: EAC = AC + WR / (CPI × SPI). Entered remaining cost: EAC = AC + manual ETC. Efficiency forecasts require positive defined indices while WR > 0.
For each available forecast, ETC = EAC − AC and VAC = BAC − EAC. With WR = 0, the first three forecasts equal AC; a separately entered positive manual ETC is retained.
For a final-cost target T, remaining allowance = T − AC. When WR > 0 and the allowance is positive, TCPI = WR / (T − AC). A nonpositive allowance is explicitly unavailable; when WR = 0, required future efficiency is not needed.
History rows are ordered cumulative observations, not period amounts to add together. Decreases are flagged as possible corrections, refunds or restatements. Horizontal chart spacing represents reporting order, not elapsed time. Use a fixed comparable baseline; no completion date or days of delay is inferred.
Entered decimal amounts use exact integer cents, and derived results use exact rational arithmetic with separate rounded displays. EAC scenarios are conditional comparisons, not probability bounds or guaranteed outcomes.

Worked Example

If you input:

  • Planning mode: Snapshot
  • Display denomination (no currency conversion): USD
  • Budget at completion (BAC): 100000
  • Planned value (PV): 40000
  • Earned value (EV): 36000
  • Actual cost (AC): 45000
  • Completion forecast: Continuing current CPI
  • Enable entered remaining cost: No
  • Compare a custom final-cost target: No

Result:

With an approved budget of $100,000, planned value of $40,000, earned value of $36,000 and actual cost of $45,000, cost variance is −$9,000 and monetary schedule variance is −$4,000. CPI is 0.8 and SPI is 0.9. Continuing the current CPI gives an estimated total cost of $125,000: $80,000 remaining cost and a −$25,000 variance against BAC. Remaining work at its budgeted rate instead gives $109,000; continuing CPI × SPI gives approximately $133,888.89. Budgeted completion is 36%, planned work is 40% and spending is 45%. Meeting the original budget would require future efficiency of 64/55, approximately 1.16364; this ratio does not establish feasibility.

Frequently Asked Questions

How are planned value, earned value and actual cost different?

Planned value is the budgeted value of work that should have been completed by the selected reporting observation. Earned value is the budgeted value of the work actually completed. Actual cost is the amount incurred for that work. Spending 50% of the budget does not establish that 50% of the work is complete. Enter progress using a consistent valuation method and comparable baseline.

Does this calculate my budget at completion?

BAC is an input: your approved budget for the complete defined scope. It is not inferred from actual cost, earned value or a forecast. Estimate at completion (EAC) is a separate scenario for final cost. A forecast above BAC indicates a modeled overrun under its assumptions; it does not automatically authorize a new budget. This planner does not manage baseline changes or reserves.

Do SPI and schedule variance show how many days late the project is?

Schedule variance here is EV minus PV in monetary units, and SPI is EV divided by PV. They compare budgeted work accomplished with budgeted work planned. They do not identify critical-path delay or a finish date. History labels are reporting labels, not parsed dates, and chart spacing shows observation order. At completion, schedule indices can cease to reveal earlier delays; use a real project schedule for time-based conclusions.

Why do the completion-cost forecasts differ?

Each forecast assumes something different about remaining work. Budgeted rate uses its original budgeted cost; CPI assumes current cost efficiency continues; CPI × SPI combines both current indices; manual ETC uses your separately entered remaining-cost estimate. These are conditional scenarios, not a statistical confidence interval. Undefined or zero efficiency cannot divide positive remaining work. When all budgeted work is earned, the first three forecasts equal actual cost, while a manual closeout-cost estimate is still retained.

Can cumulative project values decrease?

Yes. The model supports and flags decreases in PV, EV or AC between observations as possible corrections, refunds or restatements. Every observation still requires nonnegative amounts, with PV and EV no greater than BAC. It does not sum cumulative rows or calculate performance from negative period increments. Keep a fixed comparable baseline; if the baseline changes, restate the history rather than treating incompatible values as one series. For import, choose CSV or TSV and provide four columns: label, PV, EV, AC. The optional header uses those exact names and capitalization; malformed or incomplete rows reject the whole import.

What does required future efficiency, or TCPI, mean?

TCPI divides remaining budgeted work by remaining cost allowance for a chosen final-cost target. The original BAC is always compared; an optional custom target provides a second comparison. If positive work remains but the target is at or below actual cost, there is no positive remaining allowance, so no ratio is offered. If no budgeted work remains, required efficiency is not needed. A defined ratio and its comparison with CPI describe assumptions, not whether the target is achievable.

Which inputs and precision are supported?

Use one denomination for all amounts: USD, EUR, GBP or neutral units. Switching denomination is not an exchange-rate conversion. Authored amounts allow decimal or scientific notation with at most two effective decimal places, from 0 to 1e12; BAC must be positive. Currency symbols and grouping separators are not parsed. History accepts 1–60 ordered observations with nonblank labels of up to 40 characters. Exact cents and rational results are retained separately from rounded displays. This is a quantitative planner, not certified EVMS software, an accounting audit or a source of project forecasts guaranteed to occur.

What happens to optional errors and what does the CSV contain?

An invalid enabled manual remaining-cost estimate or custom target leaves valid observed status and other forecasts visible, but blocks the complete CSV until corrected or disabled. A disabled option keeps its draft. The export includes entered observations, denomination, selected reporting observation and scenario, exact and approximate quantities, forecast assumptions, correction flags and unavailable reasons. The selectable text and download use the same serialization. The methods follow the DOE and NSF earned-value references; GAO's guidance explains why monetary schedule variance is not elapsed time.