Earned Value Calculator
See how completed work and actual spending compare with your project plan. Enter a snapshot or a reporting history, then compare explicit assumptions for the cost to finish against your approved budget.
See where the project stands. Compare the cost to finish.
Connect planned work, earned work and incurred cost, then compare the assumptions behind your forecast.
Each mode keeps its own plan. All amounts in a plan use the same denomination; changing it relabels values without converting currency.
Try an example
Use the approved performance measurement baseline, excluding management reserve. Keep the same comparable baseline across history.
Amounts: 0–1e12, at most two effective decimal places; BAC must be positive. Decimal or scientific notation is accepted, without currency symbols or grouping commas.
Budgeted value of work planned by this observation.
Budgeted value of completed work. Spending alone does not establish progress.
Cost incurred for the work, which is not necessarily cash already paid.
Remaining-cost estimate and target
As of: Current snapshot
Estimated total cost (EAC)
125,000.00 USD
Current cost efficiency continues. Forecast is over BAC under this assumption.
Remaining cost (ETC)
80,000.00 USD
Variance at completion (VAC)
-25,000.00 USD
Cost performance (CPI)
≈ 0.8
Budgeted work earned per unit of incurred cost.
Schedule performance (SPI)
≈ 0.9
Budgeted work earned relative to planned work; not days ahead or late.
Cost variance (CV)
-9,000.00 USD
Incurred cost is greater than earned value.
Monetary schedule variance (SV)
-4,000.00 USD
Earned value minus planned value, in budget units.
- Budgeted work complete
- 36%
- Budgeted work planned
- 40%
- Budget spent
- 45%
Completed work and spending are different measures. BAC: 100,000.00 USD.
Budgeted work remaining: 64,000.00 USD.
Current snapshot. Estimated total cost 125,000.00 USD. Complete export available.
Planned work, completed work and cost
One common scale: 0 to 100,000.00 USD. BAC is the approved work budget.
Compare assumptions for the cost to finish
Solid blue is actual cost incurred; dashed green is estimated remaining cost. The vertical reference is BAC. Every row shares a scale ending at ≈ 133,888.89 USD. These scenarios are not a confidence interval.
Remaining work at budgeted cost
Remaining budgeted work costs one unit for each unit of its budgeted value.
- Total cost
- 109,000.00 USD
- Remaining cost
- 64,000.00 USD
- Variance against BAC
- -9,000.00 USD · over
Current cost efficiency continues · selected
The selected observation's cumulative CPI applies to remaining budgeted work.
- Total cost
- 125,000.00 USD
- Remaining cost
- 80,000.00 USD
- Variance against BAC
- -25,000.00 USD · over
Cost and progress efficiency continue
The product of the selected cumulative CPI and SPI applies to remaining budgeted work. This is a cost scenario, not a finish-date forecast.
- Total cost
- ≈ 133,888.89 USD
- Remaining cost
- ≈ 88,888.89 USD
- Variance against BAC
- ≈ -33,888.89 USD · over
Entered remaining cost
Add the separately entered estimate to complete, including any explicit closeout cost.
Unavailable: Enable and enter a remaining-cost estimate to compare this scenario.
Required efficiency for the remaining work
Meet the original budget
Final-cost target: 100,000.00 USD
≈ 1.16364
Budgeted work earned per unit of remaining cost allowance.
Remaining allowance: 55,000.00 USD. Actual cost is under this target.
Required efficiency is higher than the current CPI. Exact difference: 4/11 . This comparison does not establish feasibility.
Project status and completion forecasts
The complete export includes both exact and approximate quantities, all entered observations, selection and assumptions.
View status and exact quantities
| Quantity | Display | Exact value and unit |
|---|---|---|
| BAC | 100,000.00 USD | 100000 USD |
| PV | 40,000.00 USD | 40000 USD |
| EV | 36,000.00 USD | 36000 USD |
| AC | 45,000.00 USD | 45000 USD |
| CV | -9,000.00 USD | -9000 USD |
| SV | -4,000.00 USD | -4000 USD |
| Budgeted work remaining | 64,000.00 USD | 64000 USD |
| Budgeted percent complete | 36% | 36 % |
| Percent planned | 40% | 40 % |
| Percent spent | 45% | 45 % |
| CPI | 0.8 | 4/5 |
| SPI | 0.9 | 9/10 |
View cumulative observations and corrections
Amounts below are exact denomination values. Deltas compare adjacent supplied observations; the first has no known preceding observation. Decreases can reflect corrections and do not determine period efficiency.
| Observation | PV | EV | AC | Change in PV | Change in EV | Change in AC | Review |
|---|---|---|---|---|---|---|---|
| 1. Current snapshot · selected | 40000 USD | 36000 USD | 45000 USD | No preceding observation | No preceding observation | No preceding observation | No decrease detected |
View exact completion forecasts
| Assumption | EAC | ETC | VAC | State |
|---|---|---|---|---|
| Remaining work at budgeted cost | 109000 USD | 64000 USD | -9000 USD | over BAC |
| Current cost efficiency continues | 125000 USD | 80000 USD | -25000 USD | over BAC |
| Cost and progress efficiency continue | 1205000/9 USD | 800000/9 USD | -305000/9 USD | over BAC |
| Entered remaining cost | Enable and enter a remaining-cost estimate to compare this scenario. | |||
Selectable CSV text
Method, assumptions and sources
PV is planned budgeted work, EV is completed budgeted work, and AC is incurred cost. BAC is the approved work budget, excluding management reserve. All share one denomination and a comparable baseline. This planner does not infer progress from spending or manage changes to the baseline.
WR = BAC − EV; EAC = AC + ETC; VAC = BAC − EAC
ETC = WR, WR / CPI, WR / (CPI × SPI), or your entered estimate
TCPI = WR / (target − AC), when positive work and allowance remain
Zero denominators give unavailable indices. Positive remaining work needs positive defined efficiency for the CPI scenarios. When all budgeted work is earned, the first three forecasts equal actual cost; manual remaining cost can still include closeout costs. Monetary schedule variance and SPI do not establish days of delay, critical-path impact or a finish date. The scenario spread is not a probability interval.
Authored amounts use exact cents and derived values use exact fractions. Displays may be rounded; full fractions are in the ledger and CSV. A positive chart fraction below 0.000001 of its scale uses a limit marker rather than an ordinary zero. History decreases are flagged, not silently discarded. First-row deltas are unavailable without an earlier observation.
- U.S. Department of Energy: EVMS Gold Card — definitions and core calculation methods.
- U.S. National Science Foundation: EVM Gold Card — baseline, status and completion-cost relationships.
- GAO Cost Estimating and Assessment Guide — context and limits of earned-value analysis, including monetary schedule variance.
The input limits, correction flags and comparison states are this tool’s conventions. A calculated scenario is not an accounting audit, an EVMS certification or a guarantee of project performance.
How to use this calculator
- Choose Snapshot or Period history and a display denomination. Enter the approved Budget at completion (BAC); the calculator does not infer this baseline from spending. Changing USD, EUR, GBP or neutral units relabels amounts without converting currency.
- Enter Planned value (PV), Earned value (EV) and Actual cost (AC). For Period history, add ordered cumulative reporting observations or apply a complete CSV/TSV import, then choose the As-of observation. Cumulative decreases are allowed and flagged for review.
- Compare cost variance, monetary schedule variance, CPI and SPI. Keep budgeted percent complete separate from planned work and spending. An unavailable index has a specific reason; it is not replaced by zero or infinity.
- Choose a completion forecast: remaining work at budgeted rate, continuing CPI, continuing CPI × SPI, or an enabled entered remaining cost. Compare the assumptions and the resulting total cost, remaining cost and variance against BAC.
- Optionally enter a different final-cost target to compare required future efficiency. Correct or disable invalid enabled optional values before exporting. Inspect the selected status, history and forecast ledger, then request the CSV download or use the identical selectable text.
The Formula
The mathematical logic powering this calculation is:
BAC is the entered approved budget at completion. PV is the budgeted value of work planned by the selected observation; EV is the budgeted value of work actually completed; AC is the actual cost incurred. Amounts share one denomination.
CV = EV − AC; SV = EV − PV. Both variances are monetary. CPI = EV / AC when AC > 0; SPI = EV / PV when PV > 0. A zero denominator makes that index unavailable.
Budgeted work remaining WR = BAC − EV. Percent complete = 100 × EV / BAC; percent planned = 100 × PV / BAC; percent spent = 100 × AC / BAC. These are different quantities.
Remaining work at budgeted rate: EAC = AC + WR. Continuing current CPI: EAC = AC + WR / CPI. Continuing CPI × SPI: EAC = AC + WR / (CPI × SPI). Entered remaining cost: EAC = AC + manual ETC. Efficiency forecasts require positive defined indices while WR > 0.
For each available forecast, ETC = EAC − AC and VAC = BAC − EAC. With WR = 0, the first three forecasts equal AC; a separately entered positive manual ETC is retained.
For a final-cost target T, remaining allowance = T − AC. When WR > 0 and the allowance is positive, TCPI = WR / (T − AC). A nonpositive allowance is explicitly unavailable; when WR = 0, required future efficiency is not needed.
History rows are ordered cumulative observations, not period amounts to add together. Decreases are flagged as possible corrections, refunds or restatements. Horizontal chart spacing represents reporting order, not elapsed time. Use a fixed comparable baseline; no completion date or days of delay is inferred.
Entered decimal amounts use exact integer cents, and derived results use exact rational arithmetic with separate rounded displays. EAC scenarios are conditional comparisons, not probability bounds or guaranteed outcomes.Worked Example
If you input:
- Planning mode: Snapshot
- Display denomination (no currency conversion): USD
- Budget at completion (BAC): 100000
- Planned value (PV): 40000
- Earned value (EV): 36000
- Actual cost (AC): 45000
- Completion forecast: Continuing current CPI
- Enable entered remaining cost: No
- Compare a custom final-cost target: No
Result:
With an approved budget of $100,000, planned value of $40,000, earned value of $36,000 and actual cost of $45,000, cost variance is −$9,000 and monetary schedule variance is −$4,000. CPI is 0.8 and SPI is 0.9. Continuing the current CPI gives an estimated total cost of $125,000: $80,000 remaining cost and a −$25,000 variance against BAC. Remaining work at its budgeted rate instead gives $109,000; continuing CPI × SPI gives approximately $133,888.89. Budgeted completion is 36%, planned work is 40% and spending is 45%. Meeting the original budget would require future efficiency of 64/55, approximately 1.16364; this ratio does not establish feasibility.
Frequently Asked Questions
How are planned value, earned value and actual cost different?
Planned value is the budgeted value of work that should have been completed by the selected reporting observation. Earned value is the budgeted value of the work actually completed. Actual cost is the amount incurred for that work. Spending 50% of the budget does not establish that 50% of the work is complete. Enter progress using a consistent valuation method and comparable baseline.
Does this calculate my budget at completion?
BAC is an input: your approved budget for the complete defined scope. It is not inferred from actual cost, earned value or a forecast. Estimate at completion (EAC) is a separate scenario for final cost. A forecast above BAC indicates a modeled overrun under its assumptions; it does not automatically authorize a new budget. This planner does not manage baseline changes or reserves.
Do SPI and schedule variance show how many days late the project is?
Schedule variance here is EV minus PV in monetary units, and SPI is EV divided by PV. They compare budgeted work accomplished with budgeted work planned. They do not identify critical-path delay or a finish date. History labels are reporting labels, not parsed dates, and chart spacing shows observation order. At completion, schedule indices can cease to reveal earlier delays; use a real project schedule for time-based conclusions.
Why do the completion-cost forecasts differ?
Each forecast assumes something different about remaining work. Budgeted rate uses its original budgeted cost; CPI assumes current cost efficiency continues; CPI × SPI combines both current indices; manual ETC uses your separately entered remaining-cost estimate. These are conditional scenarios, not a statistical confidence interval. Undefined or zero efficiency cannot divide positive remaining work. When all budgeted work is earned, the first three forecasts equal actual cost, while a manual closeout-cost estimate is still retained.
Can cumulative project values decrease?
Yes. The model supports and flags decreases in PV, EV or AC between observations as possible corrections, refunds or restatements. Every observation still requires nonnegative amounts, with PV and EV no greater than BAC. It does not sum cumulative rows or calculate performance from negative period increments. Keep a fixed comparable baseline; if the baseline changes, restate the history rather than treating incompatible values as one series. For import, choose CSV or TSV and provide four columns: label, PV, EV, AC. The optional header uses those exact names and capitalization; malformed or incomplete rows reject the whole import.
What does required future efficiency, or TCPI, mean?
TCPI divides remaining budgeted work by remaining cost allowance for a chosen final-cost target. The original BAC is always compared; an optional custom target provides a second comparison. If positive work remains but the target is at or below actual cost, there is no positive remaining allowance, so no ratio is offered. If no budgeted work remains, required efficiency is not needed. A defined ratio and its comparison with CPI describe assumptions, not whether the target is achievable.
Which inputs and precision are supported?
Use one denomination for all amounts: USD, EUR, GBP or neutral units. Switching denomination is not an exchange-rate conversion. Authored amounts allow decimal or scientific notation with at most two effective decimal places, from 0 to 1e12; BAC must be positive. Currency symbols and grouping separators are not parsed. History accepts 1–60 ordered observations with nonblank labels of up to 40 characters. Exact cents and rational results are retained separately from rounded displays. This is a quantitative planner, not certified EVMS software, an accounting audit or a source of project forecasts guaranteed to occur.
What happens to optional errors and what does the CSV contain?
An invalid enabled manual remaining-cost estimate or custom target leaves valid observed status and other forecasts visible, but blocks the complete CSV until corrected or disabled. A disabled option keeps its draft. The export includes entered observations, denomination, selected reporting observation and scenario, exact and approximate quantities, forecast assumptions, correction flags and unavailable reasons. The selectable text and download use the same serialization. The methods follow the DOE and NSF earned-value references; GAO's guidance explains why monetary schedule variance is not elapsed time.
Similar Calculators
ROI Calculator
Calculate Return on Investment (ROI) to measure the profitability of any investment.
Break-Even Calculator
Find the break-even point for your business — how many units you must sell to cover all costs.
DCF Calculator
Build a professional two-stage discounted cash flow valuation with growth-stage, terminal-stage, book value, and margin-of-safety analysis.
Critical Path Calculator
Plan finish-to-start dependencies, find critical chains and compare a changed activity duration. Explore Gantt timing, waiting lags and shared float.