Welding Cost Calculator & Pilot Batch Quote Planner
Compare two logged welding pilots for the same documented fabrication scope. Estimate a target quantity using observed acceptance and whole attempts, keep setup fixed, and trace each scenario's recorded labor and consumables. See when a higher-setup option becomes cheaper for the entered batch.
Estimate welding batch cost from pilot logs
Compare measured time and resources, then scale recurring costs to the same accepted-unit target.
Measured pilot and target batch costs
Pilot B gives the lower estimated batch cost.
Estimated difference $265.00 for 100 accepted units.
Pilot A
- Measured pilot cost
- $222.60
- Observed acceptance
- 83.33% · 10 of 12
- Estimated batch cost
- $1,821.00
- Modeled attempts
- 120
- Estimated cost per target unit
- $18.21
$121.00 above budget.
Pilot B
- Measured pilot cost
- $230.00
- Observed acceptance
- 90% · 9 of 10
- Estimated batch cost
- $1,556.00
- Modeled attempts
- 112
- Estimated cost per target unit
- $15.56
$144.00 below budget.
Compare where the money goes
Paid time inside each pilot
Pilot A arc share 30%Pilot B arc share 40%
Edit Pilot A recorded work and costs
Use one completed log for the same work and acceptance basis. Enter setup time separately from recurring paid time.
Edit Pilot B recorded work and costs
Use one completed log for the same work and acceptance basis. Enter setup time separately from recurring paid time.
Review exact welding batch calculations
Pilot A
Measured fixed setup 45 USD. Measured recurring total 888/5 USD.
- Recurring labor 120 USD measured · 1200 USD for the target.
- Filler 20 USD measured · 200 USD for the target.
- Gas 30 USD measured · 300 USD for the target.
- Metered electricity 8/5 USD measured · 16 USD for the target.
- Other recurring items 6 USD measured · 60 USD for the target.
The target needs 120 attempts, so recurring costs scale by 10. Adding one fixed setup gives 1821 USD.
Pilot B
Measured fixed setup 100 USD. Measured recurring total 130 USD.
- Recurring labor 88 USD measured · 4928/5 USD for the target.
- Filler 20 USD measured · 224 USD for the target.
- Gas 16 USD measured · 896/5 USD for the target.
- Metered electricity 1 USD measured · 56/5 USD for the target.
- Other recurring items 5 USD measured · 56 USD for the target.
The target needs 112 attempts, so recurring costs scale by 56/5. Adding one fixed setup gives 1556 USD.
Show welding CSV text
How to use this calculator
- Enter the shared accepted-unit target and an optional budget.
- Enter each pilot's attempts, accepted units, recurring paid minutes and arc minutes. Record setup separately.
- Enter measured resource consumption and applicable unit prices for the same work.
- Compare measured cost with the target-batch breakdown. Review exact calculations or export a CSV.
The Formula
The mathematical logic powering this calculation is:
Use two completed pilot logs from one staffed station each with the same already-agreed workpiece and acceptance basis. Include the time and resources for rejected units and rework in the relevant pilot. Count a started workpiece once, with its final acceptance outcome. Recurring paid time covers the measured attempts and leaves the separately entered fixed setup minutes out. Arc time is their measured subset. Arc share equals arc minutes ÷ recurring paid minutes. Use measured gas volume in the same cubic-foot basis as its invoice rate.
Pilot recurring cost is paid minutes ÷ 60 × loaded labor rate, plus measured filler, gas and electricity times their rates, plus entered recurring extras. Fixed setup is setup minutes ÷ 60 × labor rate plus the entered fixed setup cost. The measured total includes both. Divide this by accepted units only when at least one unit was accepted.
Observed acceptance share equals accepted ÷ attempted. For an entered positive target, divide the target by this share and round up once to whole attempts. Multiply each measured recurring cost by projected attempts ÷ measured attempts. Add the fixed setup once. Divide batch cost by the target accepted count. The same paid activity, consumption and acceptance patterns are assumed for that scope. The projected accepted count is a model value. Use the entered budget to compare signed headroom. An exact zero headroom meets the entered budget. A pilot with zero accepted units retains measured results and gives no batch estimate.
This worksheet models recorded fabrication costs. Include only costs you want in the same quoted scope. Acceptance yield is a sample observation. Welding parameters, process and gas selection, joint design, weld qualification, safe operating requirements, approval, taxes and selling margin are outside this worksheet.Worked Example
If you input:
- Accepted target: 100 units
- Pilot A: 10 accepted from 12 attempts, $45 setup and $177.60 recurring cost
- Pilot B: 9 accepted from 10 attempts, $100 setup and $130 recurring cost
Result:
Pilot A scales to 120 attempts and $1,821. Pilot B scales to 112 attempts and $1,556. At the same target, Pilot B is $265 lower.
Frequently Asked Questions
Why do I round projected attempts up?
The model uses whole attempted units. Divide the accepted target by the observed acceptance share, then round that exact quantity up once.
Can I use arc time for the labor charge?
Use recurring paid time for labor. Arc time is an observed subset for auditing the pilot and does not set the paid amount.
What happens to a pilot with zero accepted parts?
Its measured costs and zero acceptance remain visible. A target-batch estimate needs a positive observed acceptance share.
Can a pilot with higher observed cost be cheaper at the target?
Yes. Setup is charged once, so different setup costs and per-attempt rates can change the cost order as your target changes.
Similar Calculators
Total Manufacturing Cost & Job Variance Calculator
Calculate manufacturing job costs and cost per accepted unit. Compare planned and recorded materials, labor and applied overhead and trace the difference in a waterfall.
Labor Productivity & Work Mix Calculator
Compare labor productivity across two periods. Weight completed work by standard minutes to account for job mix, then examine direct time and execution separately.
Powder Coating Color Lot & Quote Planner
Compare written powder coating bids with per-job, per-color or per-lot minimums. Track pooled parts, separate prep and masking, and price changes at lot boundaries.
First-Pass Yield & Rework Audit
Compare two production lots by stage. Separate first-pass yield, units recovered after rework, scrap, and tracked clean-through yield.
Weld Groove Filler & Package Calculator
Compare two measured single-V weld grooves. Calculate deposited volume, filler mass and whole packages using your density, transfer fraction and joint count.
