Compressed Air Demand & Receiver Planner

Explore whether receiver storage can cover a sequence of compressed-air demand bursts, and whether available compressor supply can replenish it between events. Compare up to four receiver and compressor combinations against the same ordered schedule. Follow pressure-reserve curves, inspect exact full and minimum crossing times, compare entered storage with the finite-schedule requirement, and distinguish a temporary storage shortfall from an overall supply deficit. All flow rates must share the entered ambient free-air reference. This idealized constant-temperature model starts each receiver full and assumes instantly responsive, curtailable supply. It does not predict real compressor controls, pressure losses, thermal transients or pressure-vessel suitability. Examples are illustrative, not equipment recommendations.

Compressed air demand & storage

See the bursts. Protect the reserve.

Compare receiver and compressor options over an ordered demand schedule. Find pressure-floor crossings, recharge opportunities and unmet demand.

3 minutes. Demand 90 free-air ft³. Smaller receiver: 10 free-air ft³ unserved.

Edit pressures, demand stages and options

Compare an ordered demand schedule against receiver storage and available compressor supply. All flow rates must use the same free-air reference pressure and temperature. Compressed-pipe ACFM and SCFM at other reference conditions are not interchangeable.

Pressure window and free-air basis

Absolute pressure greater than 0, up to 100 psi. The illustrative example uses 14.7 psia. Use the reference shared by every entered flow rate.

Greater than minimum, up to 1,000 psi gauge. Every option starts full at this pressure. This input does not establish a vessel rating or a recommended setting.

From 0 to below upper pressure. This is your comparison threshold, not a safety limit. Pressure-loss allowances are not added automatically.

Chronological demand stages

Stages run consecutively in this order. Enter total coincident demand, including any base load. Use separate stages for short peaks and recovery; a shift-average duty factor can hide bursts. These are entered scenarios, not measured demand predictions.

Stage 1

Up to 100 characters, such as Tool burst or Recovery.

Positive, up to 1,440 minutes. Combined duration cannot exceed 1,440 minutes. Enter 0.25 for 15 seconds.

From 0 to 1,000,000. Constant within this stage, on the shared ambient reference basis. Zero explicitly represents no demand; a blank does not.

Stage 2

Up to 100 characters, such as Tool burst or Recovery.

Positive, up to 1,440 minutes. Combined duration cannot exceed 1,440 minutes. Enter 0.25 for 15 seconds.

From 0 to 1,000,000. Constant within this stage, on the shared ambient reference basis. Zero explicitly represents no demand; a blank does not.

Stage 3

Up to 100 characters, such as Tool burst or Recovery.

Positive, up to 1,440 minutes. Combined duration cannot exceed 1,440 minutes. Enter 0.25 for 15 seconds.

From 0 to 1,000,000. Constant within this stage, on the shared ambient reference basis. Zero explicitly represents no demand; a blank does not.

Receiver and compressor options

Compare alternatives against the same schedule. Available supply is assumed constant and instantly curtailed when storage is full. Actual compressor controls, startup delays, duty limits, temperature changes and pipe losses are not modeled.

Option 1

Up to 100 characters. Describe the receiver and compressor combination.

Positive, up to 1,000,000 ft³. Enter physical internal volume, not the amount of free air stored and not gallons. This worksheet does not determine vessel suitability.

From 0 to 1,000,000, at the common reference basis. Use available delivery appropriate to this pressure window, not motor horsepower. Zero models receiver-only drawdown.

Option 2

Up to 100 characters. Describe the receiver and compressor combination.

Positive, up to 1,000,000 ft³. Enter physical internal volume, not the amount of free air stored and not gallons. This worksheet does not determine vessel suitability.

From 0 to 1,000,000, at the common reference basis. Use available delivery appropriate to this pressure window, not motor horsepower. Zero models receiver-only drawdown.

Required blanks remain invalid. Numeric inputs accept up to six decimal places. Pressure is held at the service floor for bookkeeping: unserved demand is not delivered air. Required storage covers this finite schedule starting full, not indefinite repeated operation. This is an idealized constant-temperature planning model, not pressure-vessel design or installation certification.

Storage covers peaks. Supply supports repetition.

Demand left unserved
10 ft³
Free-air volume that cannot be met above your service floor
Required receiver volume
22.05 ft³
Idealized minimum for this finite schedule, initially full
First service-floor touch
1 min
Positive shortage starts: 2.5 min
Pressure at schedule end
80 psig
Bookkeeping value bounded at your service floor

This option has a 30 free-air ft³ supply deficit per entered schedule. No finite receiver can sustain this schedule indefinitely if repeated.

All receivers start full. Constant available supply is instantly curtailed at the upper pressure. The service-floor curve is an inventory model: unserved demand is not delivered air, and real pressure after a failure is not predicted. Temperature transients, controls and pipe losses are excluded.

Pressure reserve through the schedule

Shared time axis; lines change slope at stage boundaries and exact full/minimum crossings. The vertical axis is the entered pressure window, not zero pressure.

1. Smaller receiver2. Larger receiver
Upper 100 psigTime in minutes
Receiver pressure reserve by optionExact pressure breakpoint values and shortage intervals are in the table below. Lines use distinct dash patterns as well as colors.
0 min · Floor 80 psig3 min
  • Smaller receiver: 2.5–3 min: 10 free-air ft³ unserved
  • Larger receiver: No unserved demand in this finite schedule.

Demand bursts and available supply

Peak 40 and time-weighted average 30 free-air ft³/min. Demand is the black step line; numbered option supply lines use the same patterns as the pressure chart.

40 free-air ft³/minShared time axis
Demand steps and available compressor supply
0 min · 0 free-air ft³/min3 min
Entered constant rates by stage
StageStart–end (min)Demand (free-air ft³/min)
First burst0–140
Recovery1–210
Second burst2–340

Smaller receiver: 20 free-air ft³/min available · Larger receiver: 20 free-air ft³/min available

Entered storage versus finite-schedule requirement

Physical receiver volume in ft³. Solid bars are entered volume; outlined bars are the model requirement. Shared scale: 0–29.4 ft³. A zero requirement means concurrent supply covers the entered demand, not that equipment needs no receiver.

Smaller receiver · Entered 14.7 ft³ · Required 22.05 ft³

Larger receiver · Entered 29.4 ft³ · Required 22.05 ft³

Exact stage ledger · Smaller receiver

Volumes below are free-air ft³. For every stage: starting stock + available supply + unserved demand = demand + ending stock + unused capacity. Unused capacity is potential supply not needed, not necessarily vented air or energy saved.

Exact fractions preserve the entered model precision
StageStart stockAvailable supplyDemandEnd stockUnservedUnused capacityEnd psig
First burst20204000080
Recovery02010100090
Second burst102040010080
Exact pressure breakpoints for every option
OptionTime (min)Pressure (psig)
Smaller receiver0100
Smaller receiver180
Smaller receiver290
Smaller receiver5/280
Smaller receiver380
Larger receiver0100
Larger receiver190
Larger receiver295
Larger receiver385

Save the complete comparison

CSV includes all inputs, every option, exact stage results, chart breakpoints and model assumptions, regardless of the selected option.

How to use this calculator

  1. Load Two-burst comparison or More compressor supply, then open Edit pressures, demand stages and options. Set the ambient absolute reference pressure and upper/minimum gauge pressures.
  2. Add chronological demand stages. Enter duration in minutes and total coincident free-air demand, including base loads. Use 0.25 minutes for 15 seconds. Move stages earlier or later to test ordering.
  3. Add receiver options with geometric volume in ft³ and available compressor delivery in free-air ft³/min. Ensure every flow uses the same reference conditions and is appropriate to the entered pressure window.
  4. Inspect each option’s unserved demand, pressure-floor timing and finite-schedule storage requirement. Compare pressure curves, demand steps and recharge intervals. Review the overall supply deficit separately from burst coverage.
  5. Use the exact stage and breakpoint tables, or download the compressed-air CSV. Export includes all options and assumptions regardless of the selected ledger view; selectable CSV is available as a fallback.

The Formula

The mathematical logic powering this calculation is:

Use receiver geometric volume V in ft³, free-air flow in ft³/min at the entered absolute ambient pressure Pa, time in minutes, and gauge pressures Pupper and Pminimum. All flow quantities must share the same pressure and temperature reference. Compressed-pipe ACFM and SCFM defined at other conditions cannot be substituted without an appropriate conversion. The CAGI receiver relationship is V = t × C × Pa / (Pupper − Pminimum). Concurrent supply offsets demand. This planner extends that isothermal balance over consecutive constant-rate stages.
Usable free-air capacity K = V × (Pupper − Pminimum) / Pa. Every option starts at K, corresponding to upper pressure. For each stage, net change = (available supply − demand) × duration; raw ending stock = starting stock + net change. Ending stock = min(K, max(0, raw ending stock)). Unserved demand = max(0, −raw ending stock). Unused capacity = max(0, raw ending stock − K). Unserved air is not delivered; unused capacity is potential supply not needed, not necessarily venting or energy saved.
Displayed pressure = Pminimum + usable stock × Pa / V. It is held at the service floor for inventory accounting; it does not predict actual physical pressure after unmet demand. When demand exceeds supply, a minimum crossing occurs at stage start + starting stock / (demand − supply), if the stage reaches that point. Exact endpoint equality counts as reaching minimum but does not create a positive shortfall. The first shortage time exists only when positive unserved demand follows a crossing. During net refill, upper pressure is reached at stage start + (K − starting stock) / (supply − demand). Chart lines include these exact breakpoints.
For required finite-schedule storage, start drawdown at zero. At each stage, drawdown = max(0, previous drawdown + (demand − supply) × duration). The largest drawdown is the minimum initial free-air reserve needed to avoid shortages when starting full. Required receiver volume = maximum drawdown × Pa / (Pupper − Pminimum). Stage order matters because early surplus cannot be stored above the upper pressure. Zero requirement means concurrent supply covers this schedule, not that actual equipment needs no receiver.
Total demand sums each stage rate × duration. Time-weighted average demand = total demand / total duration. Net cycle volume = available supply × total duration − total demand. A negative result cannot be sustained indefinitely by any finite receiver if the entered schedule repeats. A nonnegative result alone does not certify the chosen volume or equipment. The model does not simulate repeating control cycles.
For every stage, starting stock + available supply + unserved demand = demand + ending stock + unused capacity. The ledger and CSV preserve exact rational values; display rounding and dimensionless chart coordinates do not change the model. Required blanks remain invalid. Numeric inputs support at most six decimal places.
Bounds: 1–24 stages, 1–4 options. Ambient absolute pressure is positive through 100 psia; minimum gauge pressure is 0–1000 psig, with upper pressure strictly greater and at most 1000 psig. Physical receiver volume is positive through 1000000 ft³. Supply and demand rates are 0–1000000 free-air ft³/min. Each stage duration is positive through 1440 minutes; total duration cannot exceed 1440 minutes. These are computational bounds, not safe equipment operating limits.
The model assumes common constant temperature, initially full receivers, constant available supply and instantaneous curtailment at upper pressure. It excludes temperature transients, humidity effects, pressure-dependent delivery, compressor startup/hysteresis/duty limits, distribution losses, dryers, filters, pressure-vessel ratings, installation design and safety certification. Enter aggregate coincident demand for each stage; shift-average duty factors can hide short peaks. The service floor is user-defined, not a recommended setting.

Worked Example

If you input:

  • Pressure basis: 14.7 psia ambient; 100 psig upper; 80 psig service floor
  • Demand stages: 1 minute at 40, then 1 minute at 10, then 1 minute at 40 free-air ft³/min
  • Smaller receiver: 14.7 ft³ physical volume; 20 free-air ft³/min supply
  • Larger receiver: 29.4 ft³ physical volume; 20 free-air ft³/min supply

Result:

The schedule demands 90 free-air ft³ over 3 minutes, averaging 30 ft³/min. The smaller and larger receivers start with 20 and 40 free-air ft³ of usable reserve. Stage net changes are −20, +10 and −20 ft³. The smaller receiver first touches minimum at minute 1, refills to 90 psig at minute 2, then starts leaving demand unserved at minute 5/2 = 2.5. It ends at the bookkeeping floor of 80 psig with 10 free-air ft³ unserved. The larger option has no shortage and ends at 85 psig. Both require 30 free-air ft³ of initial reserve, equivalent to 22.05 ft³ of geometric receiver volume for this pressure window. Both have a 30 free-air ft³ supply deficit per schedule, so this sequence cannot repeat indefinitely. In More compressor supply, delivery rises to 30 ft³/min: required volume falls to 7.35 ft³ and neither option leaves demand unserved.

Frequently Asked Questions

How much compressor CFM do I need?

Start with demand rates on a common free-air basis and the timing of concurrent equipment use. This planner compares entered compressor delivery and receiver volume against those stages. It does not select compressor horsepower or infer a manufacturer’s delivery curve from motor size.

Can a larger receiver compensate for too little compressor supply?

It can cover finite bursts under the model. If the repeated schedule consumes more air than the compressor can supply over its duration, any finite receiver eventually runs out of usable reserve. A larger tank does not remove that continuing deficit.

Can I mix SCFM and compressed-pipe ACFM?

No. A volume flow at compressed line pressure is different from free-air volume flow. Even standard flow ratings can use different pressure, temperature and humidity references. Establish a compatible common basis before entering supply and demand.

Why does the pressure curve stop at my minimum?

The minimum is a service floor for inventory accounting. Any further demand that cannot be supported above it is recorded as unserved air. The flat curve does not predict real pressure after failure or claim that demand continues to be delivered.

Why can minimum pressure be reached without a shortage?

A stage can use exactly the remaining reserve at its endpoint. That touches the minimum but leaves no positive volume unmet. The next stage may refill the receiver, hold it at that level or immediately begin a shortage.

Why does changing stage order change required storage?

Surplus supply is curtailed when the receiver is full. Recovery before a burst cannot store air above the upper pressure, while recovery between bursts can restore reserve. The model follows that chronology rather than using average demand alone.

Does unused compressor capacity mean wasted electricity?

Not directly. It is potential air supply that is not needed while the receiver is full. Actual unloaded power, modulation and control behavior depend on the compressor. This calculator does not convert unused capacity into energy savings.

Is the required volume a pressure-vessel or installation recommendation?

No. It is an idealized minimum for this entered finite schedule starting full. Temperature changes, controls, distribution losses, pressure ratings, equipment duty and required design margins must be assessed separately. The user-entered pressures are not recommended operating settings.