Calculate the volume under measured rectangular baseplates using four gap readings. Add separate pocket and shoulder voids and deduct occupied volume once. Compare package quotes and see how independent pours change whole-bag demand.

Baseplate grout quantity and pours

Calculate grout volume and package demand

Use measured plate gaps, added voids and occupied volume to compare package purchases by pour.

Volume and package purchase

Option A has the lower purchase cost for separate pours.

Demand with allowance 1.34375 ft³ across 3 assigned pours.

Option A

Whole packages required
3
New packages to buy
3
Purchase cost with delivery
$89.00

Pooled volume · 3 required · $89.00

Option B

Whole packages required
6
New packages to buy
6
Purchase cost with delivery
$116.00

Pooled volume · 4 required · $84.00

Compare corner gaps at a measured plate

Front and rear baseplate gap profilesProfile 1. Front left gap 1 in. Front right gap 1.25 in. Rear left gap 1.5 in. Rear right gap 1.25 in.Gap height1.5 inLeftRight
Front faceRear face

Profile 1 · 24 × 24 in footprint · 1.25 in mean gap.

720 in³ under plate + 80 in³ added voids − 26 in³ displaced = 774 in³ net per plate.

Demand and unused mixed volume

Grout demand and whole-package capacity comparisonSeparate pours demand is 1.34375 ft³. Option A has 0.00625 ft³ left unused after rounding. Option B has 1.29625 ft³ left unused after rounding.Option AOption B0 ft³2.64 ft³
Measured demand with allowanceUnused mixed capacity

Option A 0.00625 ft³ unused.

Option B 1.29625 ft³ unused.

Edit plate profiles and pour assignments

Keep added voids outside the footprint estimate. Deduct solids occupying those counted cavities once.

Profile 1
Profile 2
Profile 3
Edit package yields, stock and prices

Use physically documented yields for the specified package and condition. Count compatible unopened stock only.

Option A
Option B
Review exact volume and per-pour package calculations

Net measured volume 43/32 ft³. Demand with 0% allowance is 43/32 ft³.

Pour 1

43/96 ft³ demand with allowance.

Option A · 1 whole packages · 1/480 ft³ unused mixed capacity.

Option B · 2 whole packages · 1037/2400 ft³ unused mixed capacity.

Pour 2

43/96 ft³ demand with allowance.

Option A · 1 whole packages · 1/480 ft³ unused mixed capacity.

Option B · 2 whole packages · 1037/2400 ft³ unused mixed capacity.

Pour 3

43/96 ft³ demand with allowance.

Option A · 1 whole packages · 1/480 ft³ unused mixed capacity.

Option B · 2 whole packages · 1037/2400 ft³ unused mixed capacity.

Show grout CSV text

How to use this calculator

  1. Enter plate footprint and measured corner gaps. Record added voids and measured displacement separately.
  2. Enter the plate count and existing pour grouping. Add the volume allowance from your takeoff, if any.
  3. Enter each documented package yield, price, usable stock and delivery charge.
  4. Compare pooled and separate pour counts or save the exact CSV.

The Formula

The mathematical logic powering this calculation is:

Enter the measured rectangular footprint of each plate and four corner gap readings in inches. The estimate assumes bilinear change between the four corners, so the exact mean modeled gap is their sum divided by four. Multiply by rectangular area to find the under-plate cavity. Separately add measured pocket and shoulder voids outside that modeled cavity. Deduct measured solid displacement already inside those volumes. A negative net cavity needs revised measurements. Model one profile per documented set of identical plates, with its quantity and assigned pour.

Multiply each net cavity by its plate count and apply the entered volume allowance once. Group profiles that share the same planned pour. There are exactly 1,728 cubic inches per cubic foot. A rectangle measuring 24 in by 36 in with a uniform measured 2 in gap occupies exactly 1 ft³ before any additions or deductions.

Use the yield for the exact package and already specified condition from the supplier. Pooled volume rounds the job’s volume divided by the entered yield up once. Separate pours round each pour up first and add those whole-package counts. In both modes usable unopened stock offsets the whole-package demand. New packages multiply by the entered price. Add the entered delivery charge only when new packages are required. Any mixed surplus is reported as volume. The separate-pour model leaves mixed surplus with its own pour.

The example yields of 0.45 and 0.44 ft³ are numerical references for documented conditions on product sheets. Prices and geometry are illustrative. Confirm that each option is already specified for the measured scope. The worksheet estimates volume and purchasing only. Installation, grout selection, mixing, cure, structural requirements and rated capacity depend on the approved project documents.

Worked Example

If you input:

  • Measured plates: Three identical 24 × 24 in plates, one per pour
  • Four corner gaps: 1, 1.25, 1.5 and 1.25 in
  • Additional voids and occupied volume: Add 80 in³ of pockets, deduct 26 in³ of solid per plate
  • Entered yield: Option A 0.45 ft³/package, Option B 0.44 ft³/package

Result:

Each plate needs 774 in³ and the job needs 1.34375 ft³. Pooled Option B needs four packages. Three separate pours need six under Option B, while Option A needs three either way.

Frequently Asked Questions

Why use four gap readings?

They describe the measured corners. The worksheet uses their average for a bilinear gap across the rectangular footprint. Deep cavities and other deviations need additional measured volume.

Why does staging require more packages?

Every separate pour rounds its own requirement up. Whole sealed stock can carry to the next pour. The separate method keeps unused mixed volume with its original pour.

Can the yield change with grout consistency or product size?

Yes. Use the documented yield for the exact package and specified condition. Enter the numeric yield from that record.

What is the difference between a pocket and displacement?

Add a measured pocket or shoulder void outside the footprint-based estimate. Deduct measured solid volume inside counted cavities. This keeps both quantities explicit and avoids double counting.