Commercial Painting Cost Calculator & Work Window Planner

Compare two written painting proposals for the same two-zone job. Enter crew application time, the coating’s confirmed recoat wait, the venue’s reopening wait and each available daily closure. Trace each coat and active visit, then compare the full-scope totals when the schedule fits.

After-hours painting

Schedule coats around reopening

Compare two written proposals using confirmed coating waits, reopening waits and active-visit charges.

Proposal A. 4 of 4 coats scheduled. Proposal B. 4 of 4 coats scheduled.

Compare painting proposals

Proposal A

4 of 4 coats scheduled

Full-scope quote
$2,280.00
Active visits
2
Last modeled release
Day 2 · 19:25
Tightest reopening slack
35 min

Proposal B

4 of 4 coats scheduled

Full-scope quote
$2,360.00
Active visits
1
Last modeled release
Day 1 · 22:20
Tightest reopening slack
40 min
Coat and reopening timelines

Each line spans one proposed closure. The upper row shows Zone 1, the lower row shows Zone 2 and the dashed line marks modeled release.

Proposal A

Closure 1

Day 1 · 18:00 to Day 1 · 23:00

3 coats, modeled release Day 1 · 22:25

Closure 2

Day 2 · 18:00 to Day 2 · 23:00

1 coat, modeled release Day 2 · 19:25

Proposal B

Closure 1

Day 1 · 18:00 to Day 1 · 23:00

4 coats, modeled release Day 1 · 22:20

Shared coat scope
Proposal A
Proposal B
Coat and visit ledger

Proposal A

Fixed quote
$1,800.00
Active-visit charges
$480.00
Application minutes
180
Proposal A closure and release details
ClosureSetup completedCleanup completedModeled releaseScheduled reopeningSlack
Closure 1Day 1 · 18:15Day 1 · 22:10Day 1 · 22:25Day 1 · 23:0035 min
Closure 2Day 2 · 18:15Day 2 · 19:10Day 2 · 19:25Day 2 · 23:00215 min
Proposal A coat times
  • Closure 1, Zone 1, coat 1, Day 1 · 18:15 to Day 1 · 19:05.
  • Closure 1, Zone 2, coat 1, Day 1 · 19:05 to Day 1 · 19:45.
  • Closure 1, Zone 1, coat 2, Day 1 · 21:05 to Day 1 · 21:55.
  • Closure 2, Zone 2, coat 2, Day 2 · 18:15 to Day 2 · 18:55.

Proposal B

Fixed quote
$2,200.00
Active-visit charges
$160.00
Application minutes
150
Proposal B closure and release details
ClosureSetup completedCleanup completedModeled releaseScheduled reopeningSlack
Closure 1Day 1 · 18:10Day 1 · 21:50Day 1 · 22:20Day 1 · 23:0040 min
Proposal B coat times
  • Closure 1, Zone 1, coat 1, Day 1 · 18:10 to Day 1 · 18:55.
  • Closure 1, Zone 2, coat 1, Day 1 · 18:55 to Day 1 · 19:25.
  • Closure 1, Zone 1, coat 2, Day 1 · 20:25 to Day 1 · 21:10.
  • Closure 1, Zone 2, coat 2, Day 1 · 21:10 to Day 1 · 21:40.
Show painting schedule CSV text

How to use this calculator

  1. Enter the confirmed coat count for each zone. Use zero coats and zero application minutes throughout for an unused Zone 2.
  2. For each proposal, enter the daily closure and reopening clocks and the number of closures available.
  3. Enter crew times and the separately confirmed recoat and reopening waits, then enter the written fixed price and active-visit charge.
  4. Compare completed coats, reopening slack and visit charges. Open the ledger to review and export the exact scheduled work.

The Formula

The mathematical logic powering this calculation is:

Each proposal uses one crew and up to 14 consecutive daily closures. A reopening clock earlier than the start clock falls on the following day. Active closures begin with setup and end when both cleanup and the entered wait from the last applied coat have elapsed. They can run in parallel once application ends, so the later one determines the modeled release. The recoat wait applies separately within each zone and continues between closures.
After setup the crew selects the whole coat with the earliest available start that can finish before the calculation’s cutoff. Zone 1 gets an exact start-time tie. The cutoff is scheduled reopening minus the longer of cleanup or reopening wait. The crew may apply a coat in the other zone while waiting to recoat. Coats do not span closures. The schedule uses this stated sequence, so another crew sequence can produce a different result.
Every closure with application adds one mobilization, and empty closures add zero. Mobilization cost = active visits × entered charge. If all coats fit, add the entered fixed full-scope price. For an incomplete scope, the worksheet shows the active-visit charges and outstanding coats separately. Reopening slack equals the deadline minus modeled release for an active closure. The tightest slack is the smallest value across those closures.
Enter one to six coats in Zone 1 and zero to six in Zone 2. Enter zero Zone 2 minutes in both proposals when Zone 2 is outside scope. Use whole minutes. Application, setup and cleanup accept up to 1,439 minutes, and waits accept up to 10,080 minutes. The fixed quote accepts $0–$1,000,000 and visit charge $0–$100,000, each with two decimals. The model covers repeated closure timing and entered prices. The coating and site teams confirm product, ventilation, actual release requirements, worker access and any maximum recoat window separately.

Worked Example

If you input:

  • Scope: Two coats each in Zones 1 and 2. Closures 18:00–23:00 for two days.
  • Proposal A: 50 and 40 min per coat, 15 min setup and cleanup each, 120 min recoat wait, 30 min reopening wait. $1,800 fixed + $240 per visit.
  • Proposal B: 45 and 30 min per coat, 10 min setup and cleanup each, 90 min recoat wait, 40 min reopening wait. $2,200 fixed + $160 per visit.

Result:

Proposal A finishes on day 2 with two visits, 35 minutes of tightest reopening slack and a $2,280.00 full-scope total. Proposal B finishes on day 1 with one visit, 40 minutes of tightest slack and a $2,360.00 total.

Frequently Asked Questions

Why are recoat and reopening waits separate?

The recoat wait controls the next coat in the same zone. The reopening wait controls when the area can be released after each active visit. Use the coating documentation and confirmed site plan for the two inputs.

What happens when a closure goes past midnight?

An earlier reopening clock falls on the next day. The worksheet carries elapsed time, recoat readiness and visits across these overnight closures.

What is an active visit?

A closure that contains at least one modeled application. An empty closure does not consume setup, cleanup or an active-visit charge.

Does matching the reopening clock qualify?

Yes. Modeled release at the exact stated reopening minute yields zero slack. Reopening one minute earlier can leave the final coat unscheduled.

Why does a partial schedule have no full-scope comparison total?

A quote total is comparable here when its schedule fits every entered coat. An incomplete option shows the visit charges at the modeled progress and the outstanding scope.