Asphalt Tonnage Calculator & Paving Ticket Audit

Use the measured footprint and specified compacted thickness and density for each lift. Assign tickets to their recorded scope and subtract only documented tare and returns. Compare completed ticket quantities with each independent review band.

Paving ticket audit

Reconcile asphalt tons by lift

Compacted lift targets

Lift 1
Lift 2

Reassign or remove tickets for the last lift before removing it.

Delivery tickets

For a ticket already recorded as net, enter that weight and zero tare. Record rejected or returned mix only once.

Ticket 1
Ticket 2
Ticket 3
Completed lifts are within their bands. Some ticket records are open.
Planned weight
40.8 short tons
All entered lifts
Retained ticket weight
41.35 short tons
Includes open ticket sets
Flagged completed lifts
0
1 set still open

Lift tonnage against the entered bands

The shaded band surrounds the planned quantity. Dots show retained ticket weight, including weights recorded for open lifts.

Lift 1

Within entered tonnage band

30 short tons planned · 30.6 short tons retained on 2 tickets

Review band 29.4–30.6 short tons

+2% from plan · 2.04 in equivalent uniform thickness

Lift 2

Ticket records still open

10.8 short tons planned · 10.75 short tons retained on 1 ticket

Review band 10.584–11.016 short tons

Review returned weight and exact lift CSV
  • Ticket 1 · lift 1
    32,000 lb net · 0 lb returned or rejected
    Exact retained weight 32000 lb
  • Ticket 2 · lift 1
    29,700 lb net · 500 lb returned or rejected
    Exact retained weight 29200 lb
  • Ticket 3 · lift 2
    21,500 lb net · 0 lb returned or rejected
    Exact retained weight 21500 lb

How to use this calculator

  1. Enter each lift’s measured area, specified compacted thickness, compacted density, and quantity review band.
  2. Add each weighed record and assign it to its corresponding lift. Account for tare and documented returns only once.
  3. Mark the ticket set complete for each reconciled lift.
  4. Review exact planned and retained tonnage, signed variances for completed lifts, and export the ledger.

The Formula

The mathematical logic powering this calculation is:

For each lift, multiply the measured area in square feet by the planned compacted thickness in inches divided by 12. Multiply that volume by the documented compacted density in pounds per cubic foot. Divide by 2,000 for US short tons. Use density for the compacted volume. Separate lifts can have different footprints, thicknesses, and densities.
Assign each scale ticket or reliably reconciled ticket group to its recorded lift once. Net delivered pounds equal gross pounds minus tare. A net-only ticket uses its net pounds as the recorded weight and zero tare. Subtract the separately documented return or rejection where applicable. A ticket already recorded after a return uses zero returned pounds. Retained pounds equal the sum of recorded net less the entered returns for that lift.
Mark a lift complete after accounting for all its relevant tickets. For completed lifts, the review band is planned pounds times 1 plus or minus the entered percent divided by 100. The exact endpoints qualify. Equivalent uniform compacted thickness in inches is retained pounds × 12 divided by the product of area and the same density used for planning. This is a mass-balance estimate over the entered footprint. It does not measure field thickness or establish how much retained material was placed. Open lifts still contribute to the entered ticket ledger. Their variance and equivalent thickness are unavailable.
Enter one to six lifts, up to 20 ticket records, areas of 1–1,000,000 ft², compacted depths of 0.001–48 in, density from 1–350 lb/ft³, and a 0–100% review band. The worksheet accepts three decimal places and uses exact quantities for comparisons. Actual installed quantities, density, pavement design, field acceptance, temperatures, specification compliance and invoiced payment are outside this worksheet.

Worked Example

If you input:

  • Lift 1: 2,400 ft² × 2 inches at 150 lb/ft³ and a ±2% review band.
  • Lift 2: 1,200 ft² × 1.5 inches at 144 lb/ft³ with records still open.
  • Tickets: 32,000 lb and 29,700 lb net for Lift 1, with a 500 lb return. Lift 2 has 21,500 lb recorded.

Result:

Lift 1 plans 30.00 short tons and retains 30.60 short tons, exactly at the upper review boundary. Lift 2 has ticketed weight but stays open.

Frequently Asked Questions

What density should I use for a planned asphalt lift?

Use the documented density that applies to the compacted volume for that lift. A loose bulk density uses a different basis.

How can I enter a ticket showing net material only?

Enter the reported net material weight and zero tare. If that same figure already reflects a return, enter zero for the return.

Why does an open lift show weight without an outcome?

The entered tickets may only cover part of the planned scope. The tool shows them while leaving the review and equivalent thickness unavailable.

Can the equivalent thickness verify the paved lift?

It spreads the recorded retained mass uniformly across the stated area at the entered density. Field verification needs actual placement, density, and thickness records.