RAID Rebuild Time & Maintenance Window Calculator

Estimate when a RAID rebuild could complete based on your own progress observations. Enter total work, current progress and recorded throughput samples under two workloads. Compare two finite schedules of active and paused stages, then inspect remaining work at your deadline without extrapolating beyond the entered schedule.

Storage operations

Compare RAID rebuild maintenance windows

Edit rebuild progress, observations and plans
Busy observation
Quiet observation
Plan A
Plan B

Only Plan A completes by the deadline.

120 GiB left · Busy 1 GiB/min · Quiet 3 GiB/min

Plan A

Completes by deadline

60 min

Modeled completion after forecast start

Remaining at deadline
0 GiB
Remaining at plan end
0 GiB

Plan B

Misses deadline

70 min

Modeled completion after forecast start

Remaining at deadline
30 GiB
Remaining at plan end
0 GiB

Inspect projected rebuild stages

Rebuild work remaining (GiB)

Deadline 60 min

  • Plan A
  • Plan B
  • After deadline

Stage 2

Plan A · Quiet · 30–65 min

3 GiB/min · 90 GiB processed

0 GiB remaining after this stage

Plan B · Paused · 20–50 min

0 GiB/min · 0 GiB processed

60 GiB remaining after this stage

Review exact rebuild stage ledger
Exact RAID rebuild progress by stage
PlanStageConditionEnd (min)Remaining before (GiB)Remaining after (GiB)Processed (GiB)
A1Busy301209030
A2Quiet6590090
A3Paused75000
B1Quiet201206060
B2Paused5060600
B3Quiet7560060

How to use this calculator

  1. Copy total work and completed work from one rebuild progress counter. Set time zero at the forecast start.
  2. Enter elapsed time and recorded start and end progress for a busy observation and a quiet observation.
  3. Enter three chronological conditions and durations for each planned schedule, plus the shared deadline.
  4. Compare projected completion and remaining work at the deadline. Inspect each stage on the common elapsed-time chart.
  5. Open the stage ledger and export your observations, assumptions and exact forecasts.

The Formula

The mathematical logic powering this calculation is:

Each measured rate equals (end progress − start progress) ÷ elapsed minutes. Busy and quiet use separate observations of the same rebuild progress counter, in GiB. The labels describe your recorded workloads. A quiet sample can be slower than a busy sample. Paused means no processed work in that scenario.
Start at total progress minus current completed progress. For each scheduled stage, multiply its rate by its duration and subtract the result from remaining work, floored at zero. If a positive-rate stage reaches zero, its completion time is stage start plus the remaining work at its start divided by its rate. If the work is complete when forecasting begins, completion time is zero. Record a deadline amount only when the schedule covers the deadline or completion is known. If the schedule ends sooner with work left, deadline coverage is unknown. Completion exactly at the deadline counts as meeting it. Time and volume comparisons use exact fractions.
Use the controller’s progress counter consistently. Enter work units from the measured rebuild or resync, rather than the sum of installed drives or files in the pool. GiB is 2³⁰ bytes. For a sector counter, use its documented sector size before expressing work in GiB. The model assumes stable representative rates for each entered workload and constant progress within its stages. Controller behavior, failures, load changes and future recovery actions are outside the forecast.
Enter total progress from 0.001–10,000,000 GiB. Completed and observed values are 0–10,000,000 GiB. Each observation is nondecreasing and ends at or before current progress. Observation and stage durations are 0.001–10,080 minutes, and the deadline is 0–10,080 minutes. Each plan has three stages. Decimal inputs allow three places.

Worked Example

If you input:

  • Starting state: 300 of 420 GiB processed. 120 GiB left. Deadline 60 min.
  • Observations: Busy advances 20 GiB in 20 min. Quiet advances 60 GiB in 20 min.
  • Plan A: Busy 30 min, quiet 35 min, paused 10 min.
  • Plan B: Quiet 20 min, paused 30 min, quiet 25 min.

Result:

Plan A finishes at exactly 60 minutes, while Plan B finishes at 70 minutes and has 30 GiB left at the deadline. Moving the deadline to 59.999 minutes leaves Plan A short by 0.003 GiB.

Frequently Asked Questions

Why is the entered total different from pool storage capacity?

The rebuild counter describes its own work. Use its displayed total and completed amount consistently. A usable capacity or file count is a different basis.

What does a blank remaining amount in the CSV mean?

An unfinished plan ends before the entered deadline. Its work beyond the modeled window has no forecast.

Must quiet progress be faster than busy progress?

The calculation uses the rates implied by the observations. Check whether each observed workload represents its projected stages.

Why can two plans finish at different times with similar total capacity?

Stage order changes when progress occurs. The projection stops counting new work once the remaining rebuild reaches zero.