Post-Construction Cleaning Cost & Visit Planner
Plan post-construction cleaning visits for three measured zones. Check each rough and final stage against released project days, contractor visit capacity and whether phases can share a visit. Compare same-scope quotes with feasible schedules.
Schedule rough and final construction cleaning
Compare written quotes across measured zones, trade handoffs and the days each crew can work.
Quote B has the lower feasible total.
1,300 ft² measured across 3 zones.
Difference across feasible totals $11.00.
Quote A
$477.00
3 visits · finishes day 6
Stage charges $312.00
Quote B
$466.00
4 visits · finishes day 6
Stage charges $286.00
Visit windows by zone
Day 2
100 of 150 crew-minutes
Zone A rough clean · Zone B rough clean
Day 4
30 of 150 crew-minutes
Zone C rough clean
Day 5
90 of 150 crew-minutes
Zone A final clean
Day 6
105 of 150 crew-minutes
Zone B final clean · Zone C final clean
Edit measured zones and access
Enter project days 1 through 90. Set an unused zone area to zero. Final cleaning follows rough cleaning on a later day.
Edit contractor quotes
Copy the written terms. Include rough and final cleaning consistently and handle touch-up separately.
Review exact visit and cost calculations
Each quote uses its own minutes and charges per 100 ft². The stage prices round to cents before adding the visit fees.
Quote A
Rough charges $104.00 · final charges $208.00.
3 × $55.00 visit fee = $165.00.
- Day 2 · 120 crew-minutes
- Zone A rough clean · 72 crew-minutes
- Zone B rough clean · 48 crew-minutes
- Day 4 · 144 crew-minutes
- Zone A final clean · 108 crew-minutes
- Zone C rough clean · 36 crew-minutes
- Day 6 · 126 crew-minutes
- Zone B final clean · 72 crew-minutes
- Zone C final clean · 54 crew-minutes
Quote B
Rough charges $91.00 · final charges $195.00.
4 × $45.00 visit fee = $180.00.
- Day 2 · 100 crew-minutes
- Zone A rough clean · 60 crew-minutes
- Zone B rough clean · 40 crew-minutes
- Day 4 · 30 crew-minutes
- Zone C rough clean · 30 crew-minutes
- Day 5 · 90 crew-minutes
- Zone A final clean · 90 crew-minutes
- Day 6 · 105 crew-minutes
- Zone B final clean · 60 crew-minutes
- Zone C final clean · 45 crew-minutes
Show cleaning plan CSV text
How to use this calculator
- Enter the measured area and released rough and final windows for each zone. Use project-day numbers and record closures.
- Copy both quotes' stage prices, labor minutes, visit cap, fee and phase mixing rules.
- Confirm the same rough and final scope before comparing prices.
- Inspect both schedule diagrams and the exact visit ledger. Adjust the blocked dates as the project changes.
- Download the inputs and visit calculations.
The Formula
The mathematical logic powering this calculation is:
Each active zone has an entered area in square feet and two independent inclusive project-day windows for rough and final cleaning. Assign each zone stage to one visit without splitting it across days. Final cleaning for a zone must happen on a later day than its rough visit. Use days 1–90 relative to the same project start and enter days that are unavailable. Set an unused zone area to zero.
The quote gives rough and final crew-minutes per 100 ft². Each stage's workload is entered area × rate ÷ 100. Each visit's crew-minute requirement is the sum of its stages. Its day must be available, lie within all of its stage windows, and use no more than the written crew-minute cap. A quote with separate phases can group rough stages or final stages together but uses a different visit for each phase. Allow mixed phases only when the written quote supports work in different zones on one visit. The crew-minute cap represents the quoted labor resource, not elapsed time.
The solver checks every permitted grouping and sequence and finds the fewest one-per-day visits within the entered limits. Among equally short visit counts it selects an earliest finish. The rough and final price subtotals each use total measured area × written dollars per 100 ft² ÷ 100, rounded to cents. Add the quoted fee once for each planned visit. Compare complete totals when both schedules fit and both quotes cover the same rough and final work. If there is no feasible schedule, the phase price subtotals remain available for review.
Use recorded zones, site release windows and written contractor terms. The examples contain illustrative rates. The worksheet covers rough and final scheduling and charges. Touch-up visits, material handling, site safety and specialty or hazardous cleanup require separate scope.Worked Example
If you input:
- Measured zones: 600, 400 and 300 ft² in separate release windows
- Quote A: Allows different-zone phase mixing, 170 crew-minutes and $55 per visit
- Quote B: Separate phases, 150 crew-minutes and $45 per visit
Result:
Quote A can finish in three visits for $477.00. Quote B uses four visits and totals $466.00. Blocking day 5 removes Quote B's feasible schedule while Quote A can still cover all stages.
Frequently Asked Questions
How can two cleaning stages use one visit?
If the written quote permits mixed phases, separate zones can share the day when all their windows, prerequisites and crew-minute limits allow it.
Can rough and final work for the same zone happen on the same visit?
This model assigns final cleaning to a distinct later day for each zone. Confirm those two project windows before using the results.
What makes a visit impossible?
One stage can exceed the labor cap or have no day available. A set of individually feasible stages can also conflict when their sequencing and daily grouping constraints are combined.
How are mobilization fees counted?
Each quote applies its entered fee once per planned visit. A visit may include multiple eligible zones.
Does the comparison count a post-punch touch-up?
The priced work comprises the entered rough and final stages. Confirm any touch-up, rework or extra visits with the contractor.
Is the smallest number of visits always the lowest modeled cost?
The stage prices stay constant in this worksheet. With a nonnegative fixed fee per visit, reducing visits minimizes that portion of the quoted cost.
Similar Calculators
Cleaning Workload & Staffing Planner
Calculate cleaning task times, weekday staffing gaps and contract costs. Compare paid shifts, visualize workload and export a complete cleaning cost ledger.
House Cleaning Visit & Contract Quote Planner
Compare house cleaning costs for the first deep clean, recurring visits, appliance extras and written skip or return fees.
Critical Path Calculator
Plan finish-to-start dependencies, find critical chains and compare a changed activity duration. Explore Gantt timing, waiting lags and shared float.
Carpet Cleaning Cost Calculator & Room Quote Planner
Compare a carpet cleaning room package with a per-square-foot quote. Match the same rooms, stairs and extras, and see the area rate where costs cross over.