Parking Lot Striping Cost & Closure Planner

Enter measured marking, removal and stencil quantities for up to five independent zones. Include each contractor's work minutes and written reopening wait. Find the least-cost grouping of complete zones for each contractor under your per-visit parking and time limits.

Pavement marking bids

Compare striping bids and closures

Group the measured zones into visits without exceeding the available stalls or time.

Quote B is $22.80 lower with staging.

Quote A
$1,635.00
2 visits cover all 3 zonesAt most 42 of 72 stalls closed
Quote B
$1,612.20
2 visits cover all 3 zonesAt most 42 of 72 stalls closed
Limits for each visit

Minimum staged cost by stall closure cap

A price appears where every zone fits. Each drop is a newly feasible combination of visits.
$1,946.00 at top$0.00 at bottom
0 stalls72 stalls

Quote A · solidQuote B · dashed

Visits and stall availability

  1. Visit 1 · Zone 1

    30 closed · 42 open · $826.00

    150 min · 15 setup + 90 work + 45 reopening wait

  2. Visit 2 · Zones 2 + 3

    42 closed · 30 open · $809.00

    170 min · 15 setup + 110 work + 45 reopening wait

Edit measured zones and contractor terms
Zone 1
Zone 2
Zone 3
Zone 4
Zone 5
Quote A written charges
Quote B written charges
Open visit and charge ledgers

Quote A visit charges

ZonesLine ftRemoval ftStencilsLine markingRemovalStencilsMinimum adjustmentMobilizationTotal
Zone 1720 ft120 ft4$324.00$180.00$112.00$0.00$210.00$826.00
Zones 2 + 3920 ft30 ft5$414.00$45.00$140.00$0.00$210.00$809.00

Quote B visit charges

ZonesLine ftRemoval ftStencilsLine markingRemovalStencilsMinimum adjustmentMobilizationTotal
Zone 1720 ft120 ft4$453.60$144.00$84.00$0.00$105.00$786.60
Zones 2 + 3920 ft30 ft5$579.60$36.00$105.00$0.00$105.00$825.60
Open selectable CSV

How to use this calculator

  1. Enter the maximum number of stalls that may be closed at once and the access window for each visit.
  2. Enable the zones in scope. Enter measured footage, stencil count, closed stalls and provider-confirmed work minutes.
  3. Enter each provider’s line rates, mobilization, minimum work charge and quoted setup and reopening times.
  4. Review the phase groupings and compare closure-cap thresholds. Download the visit and cost ledger.

The Formula

The mathematical logic powering this calculation is:

Use nonoverlapping zones from the same approved scope and measure actual billed line footage. Enter any removal billed separately and the number of separately priced stencil items. Enter each quote’s total work minutes for the zone, including indivisible tasks that the quote assigns there. A closure covers all stalls in that group for the entire visit. The worksheet treats each visit as a separate scheduling slot, with independent zones, one sequential crew and no parallel work.

For a group of zones, total minutes = setup + sum of the entered work minutes + reopening wait. Closed stalls are the sum in all zones of the group. Equality fits the entered limit for stalls or minutes. Blocking any individual zone means no grouping can cover the whole scope. The reopening wait is your written input, independent of material characteristics inferred by this calculator.

Sum line feet, removal feet and stencils by visit. Line and removal subtotals are each rounded half up to a cent after footage × price. Stencil cost is the whole count × quoted unit price. If their sum is below the minimum work charge, add the difference. Add the quoted mobilization once per visit, after that work minimum. Quote total is the sum across visits. Enter a zero charge only where it is confirmed included or waived.

The planner searches all nonoverlapping partitions of the active zones and chooses the least expensive complete plan. Exact ties prefer fewer visits, then lower closed-stall-minutes: sum of each visit’s closed stalls × full visit minutes. Remaining ties use deterministic entered-zone order. Separating work requires another site visit. The curve checks every possible combined closed-stall count plus the selected cap. No new grouping enters between consecutive subset counts. No costs are plotted below the first feasible closed-stall cap.

Supported inputs are up to five zones, 1–200 stalls, 0–30,000 ft of each linear quantity and 0–500 stencils per zone. Audited zone work is 1–720 whole minutes. The visit window is 1–1,440 minutes. This models the written billing and closure scenario only. It does not determine required markings, accessibility compliance, material drying time or traffic control procedures.

Worked Example

If you input:

  • Maximum closed stalls: 55
  • Access window per visit (min): 210
  • Zone sizes: 30, 24 and 18 stalls with separately measured striping, removal and stencils.
  • Quote A: $210 per visit after $350 minimum work; 15-minute setup and 45-minute reopening wait.
  • Quote B: $105 per visit after $280 minimum work; 20-minute setup and 35-minute reopening wait.

Result:

Both plans visit Zone 1 separately and combine Zones 2 and 3. A costs $1,635.00 and B $1,612.20. The second visit closes 42 stalls. Reduce the cap to 41 and three visits are needed.

Frequently Asked Questions

Should I estimate a separate line for each side of a parking stall?

Use the measured billable line lengths from the quote or marked plan. Shared boundaries should only be counted once unless the written scope calls for separately billed paint lines.

Does reopening wait count in the visit window?

Yes. The quoted setup, written work minutes and reopening wait all use part of the access window, and all selected stalls stay closed during that time.

Can the planner split one zone across two visits?

Zones are indivisible inputs. If the contractor can split a zone, enter the approved split as two measured zones with separate quantities.

Why can the cheapest plan use fewer visits than the time limit permits?

Each visit has a mobilization amount and may incur a minimum. The planner compares every valid grouping and preserves the smallest entered total.

Does this draw or verify a parking lot layout?

Start with measured work quantities and approved scope. This worksheet compares closure scheduling and quotes after those details are established.